No. 84CA0781Colorado Court of Appeals.
Decided November 26, 1986. Opinion Modified and, as Modified Rehearing Denied December 24, 1986.
Appeal from the District Court of the City and County of Denver Honorable Gilbert A. Alexander, Judge
Page 785
Lozow, Lozow and Elliott, Charles W. Elliott, for Plaintiff-Appellee.
Hall Evans, Jeffery B. Stalder, Alan Epstein, for Defendant-Appellant.
Division II.
Opinion by JUDGE VAN CISE.
[1] This case arises out of a 1978 construction project undertaken for the City of Denver. Defendant, Sauter Construction Co., Inc. (the general contractor), appeals the trial court’s entry of a judgment in favor of plaintiff, White Construction Co., Inc. (the sub-contractor). The general contractor also appeals the dismissal of its counterclaims against the sub-contractor. We affirm in part, reverse in part, and remand. [2] The general contractor subcontracted to Story Brothers Drywall Co. (Story) the installation of steel stud framing and drywall. Story in turn contracted the framing work to the sub-subcontractor. At the beginning of the project the sub-subcontractor was being paid by Story. [3] In August 1978, Story’s check to the sub-subcontractor was short. Thereafter, the general contractor wrote checks for payment to Story and the sub-subcontractor jointly, and the sub-subcontractor took its share for its work. The sub-subcontractor’s claim in the present case arose from work it allegedly performed in November 1978 for which it was not paid at all. [4] At trial, the court held that the sub-subcontractor had a statutory right under § 38-26-107, C.R.S. (1982 Repl. Vol. 16A) to collect $2,560 it allegedly was owed for work performed. The court also held that the general contractor’s counterclaim for $5,222 for damages based on the cost of re-doing the sub-subcontractor’s work because of its negligence was barred on the basis that there was no privity of contract between the general contractor and the sub-subcontractor. I.
[5] The general contractor first contends the trial court erred in refusing to direct a verdict in its favor on the sub-subcontractor’s claim because of the sub-subcontractor’s failure to comply with the notice requirements of § 38-26-107, C.R.S. (1982 Repl. Vol. 16A), the statute pertaining to claims for construction work on public projects. We do not agree.
Page 786
the amount of the claim, $2,560, had been withheld by Denver pending the final outcome of the lawsuit. Therefore, the trial court correctly denied the general contractor’s motion for a directed verdict.
II.
[7] The general contractor next contends the trial court erred by dismissing its counterclaim against the sub-subcontractor and by holding that this claim could be asserted only against Story. The general contractor asserts that a contractual relationship existed between it and the sub-subcontractor which would allow the assertion of a counterclaim. We agree.
Page 1250