No. 90CA0861Colorado Court of Appeals.
Decided November 7, 1991. Opinion Modified, and as Modified Rehearing Denied January 23, 1992. Certiorari Granted July 20, 1992 (92SC102).
Certiorari Granted on the following issues: Whether, on a construction project, given the existence of an escrow agreement requiring payment to be made by the principal to the escrow agent and the contractor by joint check, payment of the funds directly to the contractor alone constituted payment to a “proper party.” Where a surety seeks to recover contract funds on a public works project on which it incurred liability under §38-26-106, 16A C.R.S. (1982 1991 Supp.), and where there are remaining contract funds, whether the surety must prove that the contractor misapplied funds in order to recover under § 24-91-104, 10B C.R.S. (1988). Certiorari DENIED as improvidently granted February 23, 1993.
Appeal from the District Court of Jefferson County Honorable James D. Zimmerman, Judge.
Page 975
[EDITORS’ NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.]Page 976
Scott R. Larson, P.C., Scott R. Larson, for Plaintiff-Appellee.
Popham, Haik, Schnobrich Kaufman, Ltd., Richard G. Sander, R. Daniel Scheid, for Plaintiff-Appellee and Cross-Appellant.
Windholz Associates, James A. Windholz, William P. Hayashi, David S. Williamson; Hall Evans, Dave Brougham, for Defendant-Appellee.
Vanatta, Sullan and Sandgrund, P.C., Scott F. Sullan, for Defendant-Appellant and Cross-Appellee.
Division V.
Opinion by JUDGE RULAND.
[1] Defendant, Indiana Lumbermens Mutual Insurance Co. (Indiana), appeals the judgments entered against it and in favor of plaintiffs, SaBell’s, Inc., and Sports Facilities Contractors, Ltd., for contract and public bond claims arising out of a public works project and from the denial of its cross-claim against the City of Golden. Sports Facilities cross-appeals the amount of interest awarded on its claim. We affirm in part and reverse in part. [2] The City entered into a construction contract with Jorn Electric Corp. to make improvements to the Ulysses Park athletic field located in Golden. The improvements contracted for included landscaping and lighting. Jorn, in turn, subcontracted with SaBell’s to perform the landscaping and with Sports Facilities to install the lighting. [3] Before commencing work, and pursuant to § 38-26-101, C.R.S., (1982 Repl. Vol. 16A), Jorn was required to purchase a performance bond and a labor and material payment bond. Jorn purchased these bonds from Indiana. Indiana’s bond agent, James Misken, however, prepared a rider to the bonds and an escrow agreement. [4] This rider and the escrow agreement required the City to make payments jointly to Jorn and T.F. Bauerle, an escrow agent. Under this agreement, Bauerle was obligated to ensure that these funds were paid to the subcontractors as a form of security for Indiana. [5] Misken delivered the bonds and the escrow agreement to the director of the City’s parks and recreation department. The director supervised the project. [6] The director initially told Misken that she did not have the authority to enter into the escrow agreement but that she would contact the City’s attorney to discuss that issue. She subsequently told Misken that she had the authority to enter into the agreement and, therefore, signed it on behalf of the City. [7] The City failed to disburse the funds jointly to Jorn and Bauerle. Instead, the City paid only Jorn. Jorn failed to pay SaBell’s and Sports Facilities for all of their work, thereby defaulting on the subcontracts. Jorn also defaulted on its general contract, and consequently, the City completed the project. [8] SaBell’s and Sports Facilities brought suit against Indiana for failure to pay the remaining balance on the subcontracts and for damages pursuant to § 38-26-101, et seq., C.R.S. (1982 Repl. Vol. 16A). Sports Facilities also alleged a tort claim against Indiana. Alternatively, the subcontractors claimed damages against the City. [9] Indiana denied liability, claiming that the bonds were void because the City failed to abide by the escrow agreement. Indiana also asserted defenses based upon the statute of limitations and an alleged failure to mitigate damages. [10] In other pleadings, Indiana asserted a cross-claim against the City for indemnification. The City denied liability and filed a claim against Indiana for indemnification. [11] Following a bench trial, the trial court ruled that both SaBell’s and Sports Facilities had a right of recovery against Indiana for the amount due under their subcontracts. Also, the trial court determined that both subcontractors were entitled to eight per cent interest on the entire amount of the judgment. [12] With reference to the indemnification claims, the court ruled that Indiana had no right of indemnification against the City. It concluded that the bond rider was unenforceable as against public policy, that the director had no authority to sign thePage 977
escrow agreement, and that Indiana knew or should have known this fact. Finally, the trial court ruled that both SaBell’s and Sports Facilities were entitled to reasonable attorney fees for prosecuting their claims against Indiana because it concluded that Indiana’s defenses were frivolous and groundless.
[13] Indiana asserts that the trial court erred in various respects in resolving the contested issues at trial. It is unnecessary to resolve Indiana’s contentions relative to the bond rider. Instead, we need only address its contentions relative to the trial court’s rulings on damages, interest, and attorney fees. I
[14] The trial court found that the evidence failed to establish any damage to Indiana resulting from the City’s noncompliance with the rider and the escrow agreement. Relying upon cases such as Garcia v. Chase Manhattan Bank, 735 F.2d 645 (2d Cir. 1984), Indiana contends that its damage claim was established as a matter of law. It reasons that the claim was established simply by proving that the City made payments to someone other than the specific individuals designated in the escrow agreement. On this basis, Indiana argues that the City must indemnify it by paying Indiana the same amount the City paid Jorn. We reject this contention.
II
[17] The trial court concluded that pursuant to § 38-26-106, C.R.S. (1982 Repl. Vol. 16A), SaBell’s and Sports Facilities were entitled to eight per cent interest from Indiana on the amount not paid to them under the subcontracts. The amount of interest due was calculated from the date notice of their claims was given.
Page 978
for interest on the retainage. See South-Way Construction Co. v. Adams City Service, 169 Colo. 513, 458 P.2d 250 (1969).
[21] By the same reasoning, we conclude that the surety is not liable for interest on the retainage when the City has not withheld sufficient funds to pay all claims.III
[22] Indiana next contends that the trial court erred in ruling that the subcontractors were entitled to attorney fees because Indiana’s defenses lacked substantial justification. We agree in part.
A
[24] We conclude that it was error to award fees against Indiana for assertion of its claim that the bonds were void.
B
[32] We reject Indiana’s contention that the trial court erred as a matter of law in awarding fees against Indiana because of the complex nature of the issues presented at trial.
Page 979
[33] With reference to the statute of limitations defense, Rocky Mountain Ass’n of Credit Management v. Marshall, 44 Colo. App. 467, 615 P.2d 69 C
[37] We also agree with Indiana’s contention that the trial court must address its claim that Sports Facilities’ pursuit of a tort claim against Indiana was frivolous and groundless. Finally, we do not view any of the contentions by the parties here to be frivolous or groundless, and thus, we decline to grant any award of attorney fees for the appeal and cross-appeal.
IV
[38] Last, on cross-appeal, Sports Facilities contends that the trial court erred in not requiring Indiana to pay interest at the contractual rate of 18 per cent. In arguing for the contractual rate, Sports Facilities relies upon § 38-26-106, C.R.S. (1991 Cum. Supp.), which provides that a subcontractor shall recover “all amounts due as the result of the use of such machinery, tools, or equipment. . . .” Sports Facilities claims that the “amount due” after performing its contract, includes the contractual interest rate of 18 per cent on unpaid amounts. We disagree.
Page 980
494 P.3d 651 (2021)2021 COA 71 The PEOPLE of the State of Colorado, Plaintiff-Appellee, v.…
351 P.3d 559 (2015)2015 COA 46 DeeAnna SOICHER, Plaintiff-Appellant, v. STATE FARM MUTUAL AUTOMOBILE INSURANCE…
292 P.3d 924 (2013)2013 CO 4 Richard BEDOR, Petitioner v. Michael E. JOHNSON, Respondent. No.…
327 P.3d 311 (2013)2013 COA 177 FRIENDS OF DENVER PARKS, INC.; Renee Lewis; David Hill;…
(361 P.2d 138) THE GENERAL PLANT PROTECTION CORPORATION, ET AL. v. THE INDUSTRIAL COMMISSION OF…
Larry N. Wisehart, Plaintiff-Appellant, v. Michael Meganck and Vectra Bank Colorado, NA, Defendants-Appellees. No. 01CA1327.Colorado…