No. 85SC502Supreme Court of Colorado.
Decided April 25, 1988. Rehearing Denied June 6, 1988.
Certiorari to the Colorado Court of Appeals
Page 357
Conover, McClearn Heppenstall, P. C., Hugh J. McClearn, Catherine A. Lemon, for Petitioners.
Law Office of Robert F.T. Krassa, P. C., Robert F.T. Krassa, for Respondent.
Charles E. Grover, for Amicus Curiae Colorado Contractors’ Association, Inc.
EN BANC
JUSTICE KIRSHBAUM delivered the Opinion of the Court.
[1] In City of Florence v. Powder Horn Constructors, Inc., 716 P.2d 143(Colo.App. 1985), the Court of Appeals affirmed a trial court judgment ordering forfeiture of a bid bond executed for the benefit of the City of Florence (the City) by the petitioners, Powder Horn Constructors, Inc. (Powder Horn) and Powder Horn’s surety, St. Paul Fire and Marine Insurance Co. (St. Paul). The City filed a civil action requesting the forfeiture as damages for Powder Horn’s refusal, as low bidder, to accept the City’s award of a public improvement construction contract. Powder Horn asserted as a defense a right to equitable relief from the provisions of the bond on the ground that it had rescinded its bid; the trial court rejected this claim. The Court of Appeals held that under certain circumstances a low bidder for a public construction contract may rescind its bid, but affirmed the trial court’s judgment. Having granted certiorari to review that decision, we reverse and remand with directions.
I
[2] On December 24, 1981, the City published an advertisement for sealed bids for construction work on a water treatment facility. The bids were initially due on January 14, 1982, but that date was subsequently extended to January 19, 1982. On January 6, 1982, Powder Horn obtained a set of documents from the City detailing the engineering specifications for the project.
Page 358
sum of five percent of its total bid.[1] When the bids were publicly opened late that same day, Powder Horn was identified as the low bidder. The second lowest bid price was $754,330.
[4] The next day, January 20, Paul Gilbert, the City’s consulting engineer in charge of administering the project, telephoned Michael O’Clair, a Powder Horn estimator, and advised him that in tabulating the bids he had found one item in Powder Horn’s bid that appeared to be substantially low in view of the other bids submitted. Gilbert suggested that Powder Horn might want to review that particular item. [5] On January 21, Powder Horn’s president, Cletus Donahue, informed Gilbert by telephone that Powder Horn had mistakenly omitted from its bid the sum of $66,660, representing the cost of one major item, and that the bid was therefore being withdrawn. On that same day, Donahue also wrote a letter to Gilbert’s engineering firm in which he stated that a subtotal from one worksheet inadvertently had been omitted from the final bid amount, advised that the bid and the bid security were being withdrawn and offered to meet with the consulting engineers, the City attorney or other officials to demonstrate that the omission was an honest error. [6] On February 1, 1982, the City, through its city council, voted to award the contract to Powder Horn for the amount of $699,500. On February 4, Donahue sent a letter to Gilbert’s engineering firm stating that Powder Horn would not accept the award of the contract. The City then awarded the contract to the second lowest bidder. That bidder accepted the contract and commenced work. [7] The City filed this action against Powder Horn and St. Paul, asserting a right to the amount of the bid bond as liquidated damages for Powder Horn’s failure to execute the construction contract. The complaint alleged that although the City’s actual damages equaled $54,830, the difference between Powder Horn’s bid and the second lowest bid, Powder Horn’s liability was limited to the amount of the bid bond. Powder Horn asserted as a defense that it had rescinded its bid and therefore could not be held liable under the terms of the bid bond. [8] The trial court found that Powder Horn had not exercised reasonable care in preparing its bid. Based on this finding, it determined that Powder Horn was liable to the City in the amount of the bid bond. The trial court also determined that Powder Horn’s conduct constituted a unilateral mistake, that the mistake was material, that requiring Powder Horn to perform the contract would be unconscionable, and that Powder Horn had failed to establish that the City would not be prejudiced by the withdrawal of Powder Horn’s bid. [9] In affirming the trial court’s judgment, the Court of Appeals recognized that in some circumstances a bidder may be permitted to rescind a bid submitted for a public construction contract because of a mistake in calculating the bid. The Court of Appeals concluded that such a remedy is available only when the bidder proves by a preponderance of the evidence that: “(1) the mistake relates to a material feature of the contract; (2) it occurred despite the exercise of reasonable care; and (3) the public authority can be placed in status quo.” City of Florence v. Powder Horn Constructors, Inc., 716 P.2d 143, 144 (Colo.App. 1985). It held that Powder Horn could not rescind the bid because it had not exercised reasonable care in preparing it. The Court of Appeals also observed that a public entity which has not changed its position in reliance on a mistaken bid has suffered no actual damages and is able to maintain the status quo merely by accepting the second lowest bid “since it has lost only what it sought to gain by taking advantage of the mistake.” Id. at 145. [10] We agree with the conclusion of the Court of Appeals that under certain circumstances a bidder submitting a bid for a public construction contract may be permitted to rescind the bid prior to its acceptance if it reflects a material mistake of fact. We do not agree, however, that the exercise of reasonable care is an appropriatePage 359
factor upon which to condition this right of rescission.
II
[11] This case falls into that narrow class of public construction bid cases in which an issue of mistaken bid arises when, prior to the public entity’s acceptance of the bid, the parties discover that the bid contains a material mathematical or clerical error. Powder Horn argues that under such circumstances the bidder should be allowed to withdraw its bid automatically without penalty. A substantial body of law supports Powder Horn’s argument, in effect concluding that where a bidder submits a bid containing a material mistake of fact and the bid is apparently accepted there has not been any meeting of the minds because the bid accepted by the public entity is not the bid intended by the bidder. E.g., Moffett, Hodgkins Clarke Co. v. Rochester, 178 U.S. 373
(1900); Marana Unified School Dist. No. 6 v. Aetna Cas. Sur. Co., 144 Ariz. 159, 696 P.2d 711 (Ariz.App. 1984); Regional School Dist. No. 4 v. United Pac. Ins. Co., 4 Conn. App. 175, 493 A.2d 895, certif. denied, 196 Conn. 813, 494 A.2d 907 (1985); Baltimore County v. John K. Ruff, Inc., 281 Md. 62, 375 A.2d 237 (1977); Mississippi State Bldg. Comm’n v. Becknell Constr., Inc., 329 So.2d 57 (Miss. 1976); City of Syracuse v. Sarkisian Bros., Inc., 87 A.D.2d 984, 451 N.Y.S.2d 945 aff’d, 57 N.Y.2d 618, 454 N.Y.S.2d 71, 439 N.E.2d 880 (1982); Arcon Constr. Co. v. State, 314 N.W.2d 303 (S.D. 1982); State Highway Comm’n v. Canion, 250 S.W.2d 439 (Tex.Civ.App. 1952); see also D. Dobbs Handbook on the Law of Remedies § 11.4 (1973) (observing that, where bid contains material mistake, failure to grant bidder relief results in public authority receiving more than it was seeking in the bargain). In addition, many courts, commentators and legislative bodies have either explicitly or implicitly recognized that a mathematical or clerical error yields an unintended bid, while an error in judgment, such as an error in estimating the number of hours of work necessary to complete a project, yields precisely the bid intended and is not deemed a mistaken bid E.g., Boise Junior College Dist. v. Mattefs Constr. Co., 92 Idaho 757, 450 P.2d 604 (1969); State v. Hensel Phelps Constr. Co., 634 S.W.2d 168
(Mo. 1982); Jobco, Inc. v. County of Nassau, 129 A.D.2d 614, 514 N.Y.S.2d 108 (1987); Muncy Area School Dist. v. Gardner, 91 Pa. Commw. 406, 497 A.2d 683 (1985); see generally 10 E. McQuillin The Law of Municipal Corporations § 29.82 (3d ed. 1981); Rudland Rationalizing the Bid Mistake Rules, 16 Pub. Cont. L.J. 446 (1986); see also M.F. Kemper Constr. Co. v. City of Los Angeles, 37 Cal.2d 696, 235 P.2d 7 (1951), superseded by statute, Cal. Pub. Cont. Code § 5103
(West 1985) (where mistake made bid materially different than intended, relief available for mistake in filling out bid form, but not for mistake in judgment); N.C. Gen. Stat. § 143-129.1 (1987) (if clerical mistake, agency shall allow withdrawal of bid without forfeiture of bid security); Model Procurement Code for State and Local Governments § 3-202(6) commentary (4) (1979) (observing that bid withdrawal should be permitted where there is reasonable proof of a material mistake of fact and intended bid is not ascertainable with reasonable certainty).[2] It is undisputed here that Powder Horn’s error was not an error in judgment. Under these circumstances, there is merit to Powder Horn’s position that no agreement was or could have been consummated at the time the bids were opened.
Page 360
[12] However, this legal analysis ignores an important distinction that has emerged in the law of public contracts — the assumption that bids for public construction contracts are generally considered to be irrevocable upon opening. See Jones, The Law of Mistaken Bids, 48 U.Cin.L.Rev. 43, 45 n. 13 (1979). This principle serves to protect the integrity of the bidding process by encouraging the preparation of accurate bids, reducing possibilities of collusion and artificial bidding practices among contractors, and promoting predictability and certainty in the process of expending public funds. [13] Some jurisdictions have determined to further these policies by adopting a rule that generally prohibits rescission of a bid for a public construction contract at any time after the bids are opened. E.g., Anco Constr. Co. v. City of Wichita, 233 Kan. 132, 660 P.2d 560 (1983); City of Columbus v. Independent Towel Supply Co., 51 Ohio App.2d 250, 367 N.E.2d 915 (1977). Jurisdictions adopting this restrictive view are in the minority, however. See generally Rudland, Rationalizing the Bid Mistake Rules, 16 Pub. Cont. L.J. 446 (1986). Most jurisdictions have recognized that other important policies are also involved in the question of whether and under what circumstances a bidder on a public construction contract should be permitted to withdraw the bid. These policies include a reluctance to enforce penal forfeitures, a hesitancy to promote windfall profits in the absence of any change of position and a concern that agreements based on unilateral or mutual mistake may not represent that firm meeting of the minds that is essential to the law of enforceability of contracts. See generally Jones, The Law of Mistaken Bids, 48 U.Cin.L.Rev. 43 (1979); Rudland, Rationalizing the Bid Mistake Rules, 16 Pub. Cont. L.J. 446 (1986). [14] In view of the competing policy concerns raised in this kind of case, courts recognizing the right of a bidder to rescind a bid for a public construction contract have generally done so in the context of claims for equitable relief. See generally Rudland, Rationalizing the Bid Mistake Rules, 16 Pub. Cont. L.J. 446 (1986). The issue for these courts, as the Court of Appeals recognized, is reduced to the question of identifying the circumstances and the appropriate factors that will support a bidder’s request for relief from the consequences of a mistaken bid. We agree with the conclusion of the Court of Appeals that the more fair and responsible policy is to recognize that prior to the public entity’s acceptance of a bid for a public construction project a bidder may in some circumstances obtain equitable relief from the consequences of a bid containing a mathematical or clerical error. [15] The Court of Appeals relied principally on the case of John J. Calnan Co. v. Talsma Builders, Inc., 67 Ill.2d 213, 367 N.E.2d 695 (1977), in adopting a test that includes a requirement of proof of non-negligence to justify rescission of a public construction project bid prior to any acceptance thereof. Calnan arose in circumstances quite different from the factual context of this case, however. In Calnan, a subcontractor, John J. Calnan Co., filed an action to rescind a contract it already had entered into with Talsma Builders, Inc., a general contractor. Talsma had invited a rush bid from Calnan for the plumbing work on a public construction contract because a previous subcontractor had failed to obtain a surety bond. Calnan submitted a bid of $237,000 on May 14, 1974. The next day Calnan informed Talsma that the bid failed to reflect a $40,000 cost item for bathtubs. The parties subsequently executed an agreement based on the enhanced bid, but Calnan refused to provide a performance bond when requested to do so. In mid-September, after commencing work on the project, Calnan discovered that its original bid did not include a $31,000 cost item for the entire water supply system for the project. Calnan submitted a bill to Talsma for this sum as well as for sums allegedly due as periodic payments for work performed; when Talsma refused payment, Calnan filed an action to rescind the construction contract. Applying a three-part test to those facts, the Illinois Supreme Court concluded that CalnanPage 361
was not entitled to rescind the contract.
[16] This case presents far different circumstances. The City was aware of the “possible” mistake in Powder Horn’s bid before Powder Horn was, and Powder Horn communicated its intention to rescind its bid immediately, prior to any change of position by the City. The City did not accept the bid until later — at a time when it had full knowledge of both the mistake and the fact that because of the mistake Powder Horn had withdrawn its bid. No contract for construction of the project was ever executed by the parties, and there was no delay, no surprise, and no justifiable reliance by the City at the time it elected to accept the bid. [17] Although Calnan is distinguishable from this case, the question remains whether the formula articulated by the Illinois Supreme Court in that decision should be adopted in Colorado. That formula, as stated by the Court of Appeals, grants a bidder equitable relief from its bid if the following criteria are met: [18] “(1) the mistake relates to a material feature of the contract; (2) it occurred despite the exercise of reasonable care; and (3) the public authority can be placed in status quo.” [19] City of Florence v. Powder Horn Constructors, Inc., 716 P.2d 143, 144(Colo.App. 1985). Our inquiry is of course shaped by the particular circumstances of this case — the fact that Powder Horn’s decision to rescind its bid was made promptly upon discovery of the mistake, at a time when the City had full knowledge of the mistake and prior to the City’s decision to accept the bid. We are not persuaded that in this context the imposition of a requirement that the bidder establish freedom from negligence substantially furthers policies of encouraging fair bidding practices. To the contrary, such requirement would in these limited circumstances severely undermine policies of fostering fair dealing and certainty among contracting parties essential to any contract negotiation process. See Jones, The Law of Mistaken Bids, 48 U.Cin.L.Rev. 43 (1979). [20] The Court of Appeals concluded that requiring Powder Horn to prove it was not negligent in the preparation of its mistaken bid served to protect the integrity of the bidding process, to foster consistency in bid preparation throughout the state, and to discourage or prevent fraud and collusion. City of Florence v. Powder Horn Constructors, Inc., 716 P.2d at 145. Such salutary policies should, of course, be encouraged. However, requiring a bidder to demonstrate freedom from negligent conduct when the bid has not been accepted and the bid contains a mechanical error, as distinguished from an error of judgment, will significantly restrict the availability of this equitable remedy in circumstances wherein recognition of the remedy would not undermine those policies. Moreover, rejection of the negligence standard in these limited circumstances will foster other important policies of encouraging fair dealing by all parties to the bidding process. [21] The very term “mistake” generally connotes some degree of negligent conduct. See Mississippi State Bldg. Comm’n v. Becknell Constr., Inc., 329 So.2d 57 (Miss. 1976); Jones, The Law of Mistaken Bids, 48 U.Cin.L.Rev. 43, 70 (1979). In most circumstances it would be illogical, if not impossible, to require a bidder who has made a mistake in calculating a bid to establish that the mistake was one most reasonable bidders would make under the same or substantially similar circumstances.[3] Requiring proof of freedom from negligence
Page 362
focuses substantial attention on the cause of the mistake; the question of the availability of equitable relief from a mistaken bid should focus primarily on the consequences of the mistake. Furthermore, the three-part test articulated in Calnan would require a bidder to prove that its mistake was of sufficient magnitude to be considered material to the contract yet, incongruously, that the mistake was not the result of negligence.[4] See A. Corbin, Corbin on Contracts §§ 608, 609 (1960) (noting that an error in computing a bid invariably involves at least negligence).
[22] Numerous courts and commentators have concluded that in public construction contract cases in which a bidder seeks equitable relief from bond forfeiture provisions because of a mistaken bid, the fundamental issue is whether the bidder made an honest or good faith mistake and any question of gross or extreme negligence of the bidder should be considered only as evidence of the bidder’s lack of good faith. E.g., Marana Unified School Dist. No. 6 v. Aetna Casualty Sur. Co., 144 Ariz. 159, 696 P.2d 711; Naugatuck Valley Dev. Corp. v. Acmat Corp., 10 Conn. App. 414, 523 A.2d 924 (1987); Mississippi State Bldg. Comm’n v. Becknell Constr., Inc., 329 So.2d 57; Balaban-Gordon Co. v. Brighton Sewer Dist. No. 2, 41 A.D.2d 246, 342 N.Y.S.2d 435 (1973); State v. Union Constr. Co., 9 Utah 2d 107, 339 P.2d 421 (1959); Jones, The Law of Mistaken Bids, 48 U.Cin.L.Rev. 43, 80 (1979); Rudland, Rationalizing the Bid Mistake Rules, 16 Pub. Cont. L.J. 446, 455 (1986); cf. BCM Corp. v. United States, 2 Cl. Ct. 602 (1983) (under federal law, where public agency is on actual or constructive notice of bidder’s unreasonable mistake and accepts bid without verifying its accuracy, presumption arises that agency acted in bad faith in attempt to take advantage of bidder); see § 24-101-104, 10 C.R.S. (1982) (imposing a good faith standard upon all parties involved in state procurement activities); see also A. Corbin, Corbin on Contracts § 609 (1960) (bidding process will retain stability by requiring bidder to prove substantial mistake). This approach recognizes that a bidder should not be allowed to rescind a mistaken bid if the bid were made in bad faith and emphasizes the desirability of ensuring that public projects proceed on the basis of accurate cost estimates. A contrary rule would encourage manipulative bidding practices and undermine the stability of the bidding process. Furthermore, evenhanded application of a good faith standard ensures fair treatment of all parties involved in dealings with municipal authorities, thereby enhancing the integrity of the bidding process. [23] In this context, it is noteworthy that in adopting the Procurement Code, §§ 24-101-101 to 24-112-101, 10 C.R.S.(1982) (the Code), mandatorily applicable to state executive agencies contracting for construction projects on the basis of competitive bidding, the General Assembly has indicated that one of the public policies to be served by the provisions regulating the awarding of bids for public projects is that of ensuring the fair and equitable treatmentPage 363
of all parties to the bidding process. See § 24-101-102. Although the Code does not apply to this bidding process, its policy of ensuring good faith negotiation of public contracts is notable.[5] The degree of negligence exhibited by a bidder may well bear upon whether a bid was made in good faith, and in that respect an inquiry into the cause of the mistake may be material to the ultimate determination of whether equitable relief from a mistaken bid should be granted.[6] However, when a bid containing a clerical or mathematical error is proffered in good faith, the fact that the mistake resulted from negligent conduct should not foreclose the ability to rescind the bid prior to acceptance thereof if no harm results from the rescission.
[24] The City argued that failure to require a bidder to demonstrate freedom from negligent conduct as a condition to the exercise of any right to rescind a mistaken bid would reward careless bid preparation. However, in the competitive environment of public contracting a bidder invariably has a compelling incentive to bid accurately — to submit a bid in an amount lower than that at which the bidder can realistically perform the work is tantamount to submitting no bid at all. See Rudland, Rationalizing the Bid Mistake Rules, 16 Pub. Cont. L.J. 446, 455 (1986) (observing that a bidder gains nothing by withdrawing its bid). Far from being rewarded, a bidder allowed to rescind its bid prior to any acceptance thereof loses any possibility of reaping profit from fulfillment of the construction contract. In contrast, careless bid preparation is actually rewarded where the bidding process fails to closely circumscribe a bidder’s ability to amend its bid after opening but before acceptance. E.g., Model Procurement Code for State and Local Governments § 3-202(6) commentary (2), (3) (1979) (bidder should not be allowed to amend bid after opening unless mistake is not one of judgment and intended bid is clearly evident from bid documents). [25] In reviewing the competing policy considerations presented here, we conclude that, in the absence of controlling legislation, a bidder for a public construction contract who submits a bid containing a mistake may rescind the bid prior to its acceptance if the bidder establishes by a preponderance of the evidence that the mistake is of a clerical or mathematical nature, that the mistake was made in good faith and relates to a material aspect of the bid, and that the public authority did not rely to its detriment on the mistaken bid. If a bidder proves all of these elements, rescission of the bid should be granted because the bid apparently accepted was not the bid intended and, therefore, was not a valid bid. If, however, the bidder fails to prove each of the elements of the equitable test, the bid submitted must be deemed the bid intended and the public entity may recover proven damages to the extent the bidder fails to perform its contractual obligations — such as the public entity’s loss of bargain in being forced to forego the valid low bid and award the contract to the next lowest bidder. Such test will not undermine the integrity of the bid process, will promote fair dealing by all parties to that process and will promote contractual certainty by encouraging early discovery and disclosure of material mistakes in bids. [26] In this case, prior to advertising for bids the City’s consulting engineer estimated the total cost of the project to be $890,000 — well above Powder Horn’s bid of $699,500. Moreover, the City alerted PowderPage 364
Horn of a possible mistake when it reviewed the bids submitted and noted that on one item Powder Horn had bid $169,500, the next lowest bidder had bid $216,600 and the remaining eight bidders had bid from $230,000 to $330,000. Furthermore, Powder Horn notified the City of the nature of its mistake and its intent to withdraw the bid prior to the awarding of the contract, when no action had yet been taken in reliance on Powder Horn’s inaccurate bid and when other bids were still available to the City.
[27] These circumstances reveal an absence of one of the basic policies underlying the enforcement of contracts — if one party creates reasonable expectations in the other party, those expectations should be fulfilled, either by performance or by award of damages. See D. Dobbs, Handbook on the Law of Remedies § 11.4 (1973). Here, the City did not act upon any reasonable expectations, but rather sought to take advantage of Powder Horn’s mistake and gain a windfall profit. If Powder Horn was acting in good faith, requiring it to forfeit its bid bond even though the City knew of the mistake prior to accepting the bid would contravene fundamental principles of fairness and encourage bad faith negotiations subsequent to bid opening. See Jackson Enters., Inc. v. Maguire, 144 Colo. 164, 355 P.2d 540 (1960) (equity will not allow a party to knowingly take advantage of a mistake of another); Model Procurement Code for State and Local Governments § 3-202(6) commentary (6) (1979) (a suspected mistake can give rise to a duty on the part of the public authority to seek confirmation of bid; bidder who demonstrates mistake should be allowed to correct or withdraw bid).[7] [28] It is undisputed that the City did not solicit new bids when Powder Horn withdrew its bid and, therefore, incurred no administrative costs of rebidding the project. Cf. Board of Regents of Murray State Normal School v. Cole, 209 Ky. 761, 273 S.W. 508 (1925) (withdrawing bidder held liable to public authority for costs of rebidding the contract). The City ultimately awarded the contract to the next lowest bidder, which bid was, assuming rescission of Powder Horn’s bid, the lowest valid bid. Thus in this case the City did not change its position in reliance on the mistaken bid. E.g., Regional School Dist. No. 4 v. United Pac. Ins. Co., 4 Conn. App. 175, 493 A.2d 895 (public authority is unharmed by mistake where notified of mistake prior to award of contract), cert. denied, 196 Conn. 813, 494 A.2d 907 (1985); Boise Junior College Dist. v. Mattefs Constr. Co., 92 Idaho 757, 450 P.2d 604 (1969) (same conclusion) Mississippi State Bldg. Comm’n v. Becknell Constr., Inc., 329 So.2d 57(Miss. 1976) (same conclusion); Smith Lowe Constr. Co. v. Herrera, 79 N.M. 239, 442 P.2d 197 (1968) (same conclusion); Balaban-Gordon Co. v. Brighton Sewer Dist. No. 2, 41 A.D.2d 246, 342 N.Y.S.2d 435
Page 365
(1973) (same conclusion); see also City of Baltimore v. De Luca-Davis Constr. Co., 210 Md. 518, 124 A.2d 557 (1956) (observing that the courts were virtually unanimous in permitting withdrawal of bids where public authority was notified of mistake prior to award of contract); see also
A. Corbin, Corbin on Contracts § 609 (1960) (offeree is unharmed where notice of mistake given before acceptance of bid).
III
[31] The City argues that whatever standard might be applied to Powder Horn’s equitable claim, the parties agreed that if Powder Horn was designated the low bidder and subsequently failed to execute a construction contract Powder Horn’s bid bond was payable as liquidated damages. We find this argument unpersuasive.
(Colo. 1987); O’Hara Group Denver, Ltd. v. Marcor Hous. Sys., Inc., 197 Colo. 530, 595 P.2d 679 (1979); Perino v. Jarvis, 135 Colo. 393, 312 P.2d 108 (1957). An obligation created by a
Page 366
bond agreement will be viewed as a provision for a penalty, rather than as a liquidated damages provision, unless the bond, or other instruments to which it refers, shows that the parties intended otherwise. Turck v. Marshall Silver Mining Co., 8 Colo. 113, 5 P. 838 (1884); Moore v. Kline, 26 Colo. App. 334, 143 P. 262 (1914). Here, the bid bond provided in pertinent part as follows:
[34] “BID BOND
[35] “. . . [W]e, the undersigned, POWDER HORN CONSTRUCTORS, INC. . . .as Principal, and ST. PAUL FIRE AND MARINE INSURANCE COMPANY as Surety, are hereby held and firmly bound unto CITY OF FLORENCE, COLORADO as OWNER in the penal sum of Five Percent (5%) of the Total Amount of Bid
[44] “BID
[45] . . . .
This document
Page 367
does not suggest that the five percent bid bond was intended by either party to represent an agreed amount of liquidated damages or that the actual damages from a bidder’s failure to execute a construction contract might be regarded as the difference between a withdrawn low bid and the next lowest bid. Cf. Bellefonte Borough Auth. v. Gateway Equip. Supply Co., 442 Pa. 492, 277 A.2d 347 (1971) (where informational documents given to prospective bidders stated that bidder failing to execute construction contract would forfeit amount of bid bond as liquidated damages, bid bond constituted liquidated damages rather than penalty). Although the document does prohibit the withdrawal of bids within sixty days of the opening of the bids,[10] it also authorizes the City to waive minor defects in bids or to reject any and all bids. It does not indicate that the bond must be forfeited as liquidated damages if any of its terms are not followed.
[51] It appears from the terms of the bid bond and from the provisions of the accompanying documents that the purpose of the bid bond is to compel the execution of a construction contract by the threat of exacting a payment in the amount of the bond as a punishment for failure to execute such a contract. See 2 G. Palmer, The Law of Restitution § 12.20, at 689 (1978) (“the purpose of the contract formed by the bidPage 368
bond . . . is to give some assurance that the bidder will enter into a performance contract if his bid is accepted”).
[52] In ascertaining the purposes to be accomplished by a contract, one may also consider the circumstances surrounding the making of the contract I.M.A., Inc. v. Rocky Mtn. Airways, Inc., 713 P.2d 882 (Colo. 1986) Lorenzen v. Mustard’s Last Stand, Inc., 196 Colo. 265, 586 P.2d 12 (1978). At trial, the City presented no evidence respecting the circumstances surrounding the execution of the bid bond and accompanying documents which would indicate that a purpose of the bid bond was to establish a liquidated damages sum.[11] Construing the bond documents together, as we must, it is clear that the parties intended the bid bond to constitute a penal sum. In the absence of any evidence in the record demonstrating that the purpose of the bond was to liquidate damages, we conclude that the parties did not mutually intend to liquidate damages, see Rohauer v. Little, 736 P.2d 403 O’Hara Group Denver, Ltd. v. Marcor Hous. Sys., Inc., 197 Colo. 530, 595 P.2d 679; Perino v. Jarvis, 135 Colo. 393, 312 P.2d 18. Rather, the bid bond as agreed upon by the parties here must be deemed a penal bond.[12] IV
[53] The City also argues that under the terms of section 31-15-712, 12B C.R.S. (1986), it was compelled to award the construction contract to Powder Horn. We are not persuaded by the City’s argument.
(1914), the Court of Appeals concluded that under the predecessor to section 31-15-712 a municipality could be held liable for a public improvement contract only if the contract was an express contract and was approved by a majority of the city council or board of trustees. The plaintiff in that case alleged that he had superintended a public construction project, but failed to allege in his complaint that he had an express contract with the public authority. The City asserts that in light of the Coray decision section 31-15-712 must be read to require a municipality
Page 369
to award the construction contract to the lowest bidder even where that bidder inadvertently makes a substantial computational error. We cannot agree that the Coray decision necessarily compels such a conclusion. I Coray the Court of Appeals did not have before it the question of whether a municipality which properly put a project up for bids could forego awarding the contract to a bidder on the common law basis of mistake See City County of Denver v. Bowen, 67 Colo. 315, 317, 184 P. 357, 358
(1919). Moreover, the General Assembly has specifically provided that in the construction of statutes the common law shall remain in full force until repealed by legislative authority, § 2-4-211, 1B C.R.S.(1980), and section 31-15-712 does not by its terms purport to repeal the common law respecting mistakes in the formation of contracts.
of the Code, a provision specifically dealing with bid bonds, provides in pertinent part as follows: [60] “Bid security. (1) Bid security shall be required for all competitive sealed bidding for construction contracts when the price is estimated by the procurement officer to exceed fifty thousand dollars. . . . Nothing in this subsection (1) prevents the requirement of such bonds on construction contracts under fifty thousand dollars. [61] “(2) Bid security shall be in an amount equal to at least five percent of the amount of the bid. [62] . . . . [63] “(4) After the bids are opened, they shall be irrevocable for the period specified in the invitation for bids, except as provided in section 24-103-202(6). If a bidder is permitted to withdraw his bid before award, no action shall be had against the bidder or the bid security.” [64] § 24-105-201, 10 C.R.S. (1982). These provisions of the Code demonstrate a clear legislative intent to allow bidders who have inadvertently erred in the preparation of their bids to withdraw those bids before award of the contract without loss of bid bond. Although application of the Code provisions is mandatory only with respect to bodies of the state executive branch, section 24-101-105(2) of the Code specifically grants municipal authorities the power to apply any or all provisions of the Code. We conclude, therefore, that the City’s contention that it was compelled by statutory law to award the contract to the lowest bidder even where that bid contained an inadvertent error is without merit.
V
[65] The judgment of the Court of Appeals is reversed, and the case is remanded to the Court of Appeals with directions to reverse the judgment of the trial court and to remand the case to the trial court for determination of whether Powder Horn’s bid was made in good faith. In the event the trial court determines the mistake was made in good faith, judgment should be entered for Powder Horn and against the City. In the event the trial court
Page 370
determines the mistake was not made in good faith, judgment should be entered for the City and against Powder Horn on the basis of the bond.
[66] JUSTICE ERICKSON dissents. [67] JUSTICE VOLLACK dissents; JUSTICE MULLARKEY joins in the dissent.Restatement of Restitution § 59 (1936) (person who mistakenly conferred benefit upon another is not precluded from restitution where mistake was due to lack of care); D. Dobbs, Handbook on the Law of Remedies § 11.2 (1973) (concluding that a negligent party should be relieved from a mistake unless the nonmistaken party suffers prejudice); Rabin, A Proposed Black-Letter Rule Concerning Mistaken Assumptions in Bargain Transactions, 45 Tex.L.Rev. 1273, 1278-1279, 1283 (1967) (concluding that the better rule is that relief from mistake should depend on the inequality of the exchange rather than the negligence of the mistaken party).
(Colo.App. 1985) (relying upon John J. Calnan Co. v. Talsma Builders, Inc., 67 Ill.2d 213, 367 N.E.2d 695 (1977)). The irrevocability of the bid is, to an extent, supported by the “Information for Bidders” section of the bid contract which provides that: “No BIDDER may withdraw a BID within 60 days of the actual date of the opening thereof.” [72] While I acknowledge that the John J. Calnan Co. case is distinguishable on its facts from this case, I believe that it provides the best formula for balancing the need to preserve the trial court’s ability to grant the equitable remedy of rescission in meritorious cases, against the need to preserve the integrity of the bidding process and to diminish the frequency of fraud, collusion, and careless bid preparation. [73] The majority questions whether any legitimate purpose is served by requiring a bidder to establish freedom from negligence, asserting that “such requirement would in these limited circumstances severely undermine policies of fostering fair dealing and certainty among contracting parties essential to any contract negotiation process.” Slip op. at 12. The majority asserts that requiring a lack of negligence “focuses substantial evidence on the cause of the mistake,” when primary focus should be given to the “consequences of the mistake.” Slip op. at 13. Accordingly, the majority concludes that in order to rescind the bid Powder Horn must establish a “good faith mistake.” Slip op. at 20. [74] In my view, simply requiring a contractor to submit a bid in good faith compromises the integrity of the bidding process by failing to penalize sloppy bid preparation and by failing to discourage fraud by contractors who seek to rescind a bid that is not the product of clerical error but rather a mistake in judgment on the contractor’s part. A majority of jurisdictions has adopted the requirement that a contractor demonstrate that he exercised reasonable care before he is allowed to rescind a bid. See 10 E. McQuillin, The Law of Municipal Corporations § 29.67, at 383 (3d ed. 1981); Annotation, Right of Bidder for State or Municipal Contract to Rescind Bid on Ground That Bid Was Based Upon His Own Mistake or That of His Employee, 2 A.L.R.4th 991, 1003-13 (1980). [75] In this case, it is conceded that Powder Horn’s $73,326 error was material, thus satisfying the first element of the three-part test set forth by the court of appeals. With respect to the negligence element, the trial court concluded that Powder Horn failed to exercise reasonable care in preparing its bid. Because this finding is supported by the record, see
slip op. at 4-6 (Vollack, J., dissenting), we will not disturb it. We need not address the third element because Powder Horn failed to exercise reasonable care in preparing its bid. [76] While I believe that under the bid bond the City is limited to actual damages not to
Page 371
exceed the limits of the bond, I am not convinced that the court of appeals or the trial court considered the actual damages suffered by the City. See City of Florence, 716 P.2d at 145. Accordingly, I would return the case to the court of appeals for remand to the district court to determine actual damages suffered by the City.
I.
[70] The majority concludes that
Page 372
evaluation of the subjective intention of the parties. In order to demand rescission of a negligently prepared bid under the majority’s rule, the low bidder need only prove an absence of bad faith, which is to say, that the bid was submitted without an intent to defraud. To refute such a claim, the City would have to show that the low bidder acted in bad faith through dishonesty. Such a standard would allow a bidder to escape responsibility for conduct that might well have been prevented by exercising reasonable care and would impose an impossible evidentiary burden on the City to circumvent.
[77] “[T]he standard of good faith for merchants is one which can be asserted in a variety of circumstances, and is often used as a sword in avoiding liability . . . . It is a standard that is difficult to deal with and hard to define in any given situation, and is used creatively in a variety of contexts to challenge rights and liabilities under sales contracts.” [78] 3 R. Duesenberg L. King, Sales Bulk Transfers Under The Uniform Commercial Code § 4.08[3][a][ii], at 4-267 to -269 (1987) (footnotes omitted).II.
[79] Requiring a contractor to show that his error occurred despite the exercise of reasonable care as a condition precedent to rescission of a public construction contract is a sensible alternative to a good faith rule. In fact, it appears to be the rule in a majority of jurisdictions See 10 E. McQuillan, The Law of Municipal Corporations § 29.67, at 383 (3d ed. 1981); 3 J. Pomeroy, A Treatise on Equity Jurisprudence § 870a, at 388 (5th ed. 1941); Annotation, Right of Bidder for State or Municipal Contract to Rescind Bid on Ground that Bid Was Based Upon His Own Mistake or That of His Employee, 2 A.L.R.4th 991, 1003-13 (1980).
Page 373
[81] “It is of paramount importance that the integrity of the bidding process not be compromised by those entrusted with providing the state’s citizens the improvements that public policy and the law command. In interpreting the requirements of the bidding process the court must keep in mind that the procedures `are designed to prevent fraud, collusion, favoritism and improvidence in the administration of public business as well as to insure that the public receives the best work or supplies at the most reasonable price practicable.'” [82] Dillingham Constr., Inc. v. Milwaukee Metro. Sewerage Dist., 629 F. Supp. 406, 409 (E.D. Wis. 1986) (quoting Nelson, Inc. v. Sewerage Comm’n, 72 Wis.2d 400, 409, 241 N.W.2d 390, 395 (1976)). [83] The majority recognizes that Powder Horn’s bid was negligently prepared. It nevertheless minimizes the role that reasonable care plays in the public bidding process by stating that “[t]he very term `mistake’ usually connotes some degree of negligent conduct.” Slip op. at 13. [84] Contrary to the majority’s intimation, reasonable care has never been equated with absolute blamelessness. Rather, the question of whether a mistake constitutes negligence depends on the circumstances and requires an objective comparison of particular conduct to what a reasonably prudent person would do in the same situation in light of the recognized risk associated with it. See W. Keeton, Prosser and Keeton on the Law of Torts § 31, at 170-73 (5th ed. 1984); Restatement (Second) of Torts §§ 282, 283 (1965). In the area of mistaken bids, I believe the most useful standard for determining whether a mistake constitutes negligence is the standard practice or custom in the construction industry.[2] It is undisputed that failure to observe industry standards of reasonable care is evidence of negligence. See W. Keeton Prosser and Keeton on the Law of Torts § 33, at 195 (5th ed. 1984). Powder Horn’s conduct falls short of those standards. [85] Cletus Donahue, Powder Horn’s president and bidder on the Florence project, testified that he could have picked up the specifications for the Florence project from the City on December 24, 1981, but chose to wait until January 6, 1982, to do so. This reduced from twenty-seven to fourteen the number of days Powder Horn had to prepare its bid. [86] The Florence project estimator, Michael O’Clair, calculated the cost of concrete and labor associated with wall forming for the Florence project on page fifteen of his bid book. The bid book was a three ring binder that permitted removal of all of its pages. O’Clair testified that the estimates on page fifteen were completed on January 18, more than twenty-four hours before the erroneous bid was submitted. The missing page had been removed from the bid book on January 19, even though no changes were subsequently made to it. [87] O’Clair admitted that he failed to fill in three of the preprinted blank spaces on the missing page fifteen. These blanks included space for the estimator to fill in his initials, to recheck his original estimate, and to total the costs on the page. Neither he nor Donahue, Powder Horn’s other estimator, had double-checked his page fifteen estimate of the cost of labor and concrete for the Florence project. [88] Following a bench trial, the trial judge found that waiting two weeks to pick up the specifications, removing pages from the bid book that did not need last-minute revision, and failing to use the series of checks built into its system, made Powder Horn’s mistaken bid a product of negligence. In fact the trial judge suggested that Powder Horn’s bidding procedure may have constituted gross negligence.[3]Page 374
[89] Errors in calculating a bid can occur despite the exercise of reasonable care on the part of the contractor. When such errors occur despite the exercise of reasonable care, I believe that rescission is an appropriate remedy to consider as long as the mistake also relates to a material feature of the contract and rescission could return the City to the position it was in before accepting Powder Horn’s bid. See, e.g., John J. Calnan Co. v. Talsma Builders, Inc., 67 Ill.2d 213, 367 N.E.2d 695(1977). That this error was due to Powder Horn’s negligence increases my belief that rescission of the contract is not the appropriate remedy in this case.
III.
[90] The majority correctly concludes that section 24-103-202(6) does not prohibit the City from permitting Powder Horn to rescind the contract. This analysis nevertheless overlooks the more important question of whether in such circumstances the City is required to permit the contractor to rescind the contract. The clear language of section 24-103-202(6) shows that the General Assembly never intended to prohibit municipalities such as the City[4] from enforcing a contract based on a mistaken bid.
Page 375
[92] Requiring Powder Horn to show that its error occurred despite the exercise of reasonable care is faithful to the policy considerations that underlie the Colorado Procurement Code. Section 24-101-102 recites the underlying purposes and policies of Colorado’s version of the Model Procurement Code. These purposes and policies are: [93] “(a) To simplify, clarify, and modernize the law governing procurement by the state of Colorado; [94] “(b) To provide for increased public confidence in the procedures followed in public procurement; [95] “(c) To ensure the fair and equitable treatment of all persons who deal with the procurement system of the state of Colorado; [96] “(d) To provide increased economy in state procurement activities and to maximize to the fullest extent practicable the purchasing value of public funds of the state of Colorado; [97] “(e) To foster effective broad-based competition within the free enterprise system; and [98] “(f) To provide safeguards for the maintenance of a procurement system of quality and integrity.” [99] 10 C.R.S. (1982). [100] Permitting bid withdrawal for mistakes that occur despite the exercise of reasonable care ensures fair treatment of low bidders by relieving them of burdens caused by mistakes they could not reasonably have prevented. Requiring bidders to conform bids to the industry standards of reasonable care maintains the integrity of the bidding process, and in turn increases public confidence in the procedures followed in public procurement. [101] A good faith rule that permits rescission of contracts for careless errors in bids, by contrast, would undermine the policy considerations outlined in the Procurement Code. Careless bids diminish the purchasing value of public funds in violation of section 24-101-102(2)(d). A low bidder has an economic incentive to bring to the attention of the public authority any error whose actual cost for a given item exceeds its estimated cost, resulting in a net loss to the bidder for that item. Yet a low bidder has no corresponding incentive to bring to the attention of the public authority an error resulting in a net gain to the bidder because he has already been awarded the contract. Accordingly, the purchasing value of public funds can be diminished but not increased by permitting rescission of carelessly computed bids. [102] Careless bids also lower public confidence in the procedures followed in public procurement in violation of section 24-101-102(2)(b). A low bidder would receive the opportunity, denied to all other bidders, to reconsider his bid in light of competitors’ bids which are known to be higher than his and which are required to remain available for public inspection by custom and, in those municipalities that have adopted the Procurement Code, by statute. See, e.g., § 24-103-202(4), 10 C.R.S. (1982). Rescission could then become simply another business option in the event that an opportunity to make a larger profit arises after the bids are open. Even the possibility of such an option would erode public confidence in the public procurement process. That the public authority could not prevent rescission by showing that the mistake was due to the bidder’s negligence would further undermine that public confidence. [103] Finally, permitting contractors to rescind carelessly prepared bids would confuse rather than simplify public procurement in violation of section 24-101-102(2)(a) by introducing greater uncertainty into the bid process. Public authorities could no longer consider the bid process complete when the bids were opened. Bids could no longer be considered irrevocable for the time period specified in the invitation for bids as required by contract between the parties, by custom in the industry, and by statute in those municipalities that have adopted the Procurement Code See, e.g., § 24-105-201(4), 10 C.R.S. (1982). The good faith rule adopted by the majority could conceivably cause public authorities to accelerate the formal acceptance processPage 376
to the time of bid opening so as to remove the uncertainty that the good faith rule creates.
IV.
[104] Finally, the majority’s rule gives insufficient consideration to the public character of the bidding process. Unlike bids in the private sector, bids in the public sector must be awarded to the lowest responsible bidder. § 31-15-712, 12B C.R.S. (1986).[7] Although the City has not adopted the Procurement Code, its contract with Powder Horn contains the same elements. The informational document provided to all bidders and incorporated by reference into the bid contract requires each applicant to submit a sealed bid which may not be revoked for sixty days after opening. Each bid must be accompanied by a bid bond for five percent of the total amount of the bid. Bids must be opened publicly and read aloud in accordance with the advertisement for bids. As the Procurement Code recognizes, these elements are designed to maintain the integrity of the bidding process. In addition, the informational document incorporated into the bid contract states that
Page 377