No. 93CA1160Colorado Court of Appeals.
Decided December 29, 1994. Petition for Rehearing DENIED March 9, 1995. Petition for Writ of Certiorari Denied September 25, 1995.
Appeal from the District Court of the City and County of Denver Honorable H. Jeffrey Bayless, Judge No. 92CV8100.
JUDGMENT AFFIRMED.
Page 422
McAllister Murphy, P.C., Robert T. McAllister, Kathryn Haight Meyer, Denver, Colorado, for Plaintiff-Appellant.
Daniel E. Muse, City Attorney, Steven J. Niparko, Assistant City Attorney, Denver, Colorado, for Defendants-Appellees.
Division V.
Briggs and Taubman, JJ., concur.
Opinion by JUDGE RULAND.
[1] Plaintiff, Kiewit Western Co., appeals from a judgment dismissing its complaint for declaratory and other relief against defendants, City and County of Denver, the Department of Public Works (Department), and Michael Musgrave in his capacity as acting Manager of the Department. We affirm. [2] The Department advertised for sealed bids to excavate for two runways at the Denver International Airport. It determined that plaintiff’s bid was the lowest responsive bid for each of the runways, and accordingly, it awarded plaintiff both contracts. One of the contracts required payment to plaintiff in the approximate amount of $45 million and the other in the approximate amount of $23 million. [3] Each of the contracts contained a “changes in the work” procedure for plaintiff to obtain additional compensation. Specifically, claims for additional compensation were permitted if plaintiff discovered design errors, if it encountered differing site conditions than those represented by defendants, if there was delay in the progress of the work caused by defendants, and if any other circumstance arose which necessitated a change in the time of performance or payment. [4] The contracts specified time limits for submitting change orders requesting additional compensation. Each request was first reviewed by the Resident Engineer. If denied, the request had to be submitted to the Construction Manager. Upon denial by that official, a protest was required to the Assistant Director of Aviation, and thereafter to the Manager of Public Works (Manager). [5] If a claim for additional compensation was ultimately denied, the contracts provided that “disputes regarding this contract shall be resolved by administrative hearing under [the] procedures described in [Denver] Revised Municipal Code Section 56-106.” This provision authorized the Manager to designate a hearing officer to conduct a hearing relative to any dispute. The hearing officer’s decision was binding unless a written request for review by the Manager was made. [6] If the Manager approved a decision of the hearing officer adverse to plaintiff, plaintiff was authorized to seek judicial review pursuant to C.R.C.P. 106. [7] Plaintiff filed its complaint asserting 14 claims for relief. In its first two claims, plaintiff asserted that the claims submissions and dispute resolution procedures described above (the Procedures) were ultra vires as not authorized by the Colorado Constitution and the Denver City Charter. Plaintiff also alleged that the Procedures violated plaintiff’s rights to due process under the Colorado and United States Constitutions because a fair and impartial hearing procedure was not required at the administrative level. [8] In its remaining claims for relief, plaintiff alleged that defendants were guilty of misrepresentations concerning the project prior to submission of plaintiff’s bid and in conjunction with certain change orders. Plaintiff also alleged that defendants breached both implied warranties relative to site conditions and the covenant of good faith and fairPage 423
dealing, and had imposed “cardinal changes” to the work not contemplated by the original contracts.
[9] On the basis of these allegations, plaintiff requested that it be awarded a quantum meruit recovery and damages. [10] In response to the complaint, defendants filed a motion to dismiss pursuant to C.R.C.P. 12(b)(5). As pertinent here, defendants requested that the first two claims for relief be dismissed on the basis that the Procedures were valid and binding. Defendants requested dismissal of the remaining claims on the basis that plaintiff had failed to follow the Procedures in the contracts and that, therefore, plaintiff had failed to exhaust its contractual remedies. [11] Based upon the parties’ submissions, the trial court agreed with both of defendants’ contentions and dismissed the complaint. I
[12] Plaintiff first contends that the trial court erred in dismissing its first claim for relief based upon the conclusion that the Procedures contained in the contracts were authorized by Colo. Const. art. XX, § 1 and Denver City Charter ch. A, art. II. Each of the cited provisions addresses the construction of Denver’s public works but neither specifically authorizes the City to include the Procedures in public works contracts. We conclude that it is unnecessary to address this contention.
Page 424
the Procedures are ultra vires as not authorized by the Colorado Constitution and the Denver City Charter.
II
[21] Plaintiff contends that the trial court erred in dismissing its second claim for relief which challenged the Procedures as violating plaintiff’s rights to compensation under the due process clauses of the Fourteenth Amendment and Colo. Const. art. II, § 25. Specifically, plaintiffs argue that the allegations of this claim establish that the Procedures fail to provide a full, timely, and fair review of any claim for additional compensation. We agree with the trial court’s ruling.
(Ct.Cl. 1967); C.J. Langenfelder Son, Inc. v. United States, 341 F.2d 600 (Ct.Cl. 1965). [27] Applying those principles here, we conclude that plaintiff’s allegations that the Procedures are complex, potentially time consuming, and that the decision makers are employed by Denver fail to state a claim for a due process violation. [28] This leaves for resolution plaintiff’s conclusionary allegation that unspecified claims
Page 425
were submitted for resolution and “summarily rejected . . . due to the bias and partiality of said agents or representatives in favor of Denver.”
[29] If it is determined that the government official has acted with bias the decision may be set aside. See C.J. LangenfelderSon, Inc. v. United States, supra; In re Winchester, 133 B.R. 368 (Bankr. N.D. Miss. 1991) (state administrator communicated to plaintiff that further claims or appeals would be rejected for the same reasons as previous claims). [30] However, in our view, plaintiff may not avoid following the Procedures by simply making a conclusionary allegation of bias occurring at some stage of the Procedures with reference to some unspecified claim or claims. Otherwise, the Procedures could be avoided in every case by making that allegation. See Carr v. Pacific Maritime Ass’n, 904 F.2d 1313 (9th Cir. 1990), cert. denied, 498 U.S. 1084, 111 S.Ct. 957, 112 L.Ed.2d 1045 (1991); Newport News Shipbuilding Dry Dock Co. v. United States, supra; see also Hoffman v. State Board of Assessment Appeals, 683 P.2d 783 (Colo. 1984) (taxpayer must exhaust existing and adequate statutory remedies before seeking judicial relief); Leete v. State Board of Medical Examiners, 807 P.2d 1249
(Colo.App. 1991)(plaintiff’s declaratory judgment action dismissed for failure to exhaust disciplinary administrative procedures). This is especially so in the due process context because, as noted by the trial court, demonstrated bias would constitute grounds for judicial reversal of the decision pursuant to C.R.C.P. 106(a)(4). [31] Accordingly, here, plaintiff’s allegations in its second claim for relief are not sufficient to state a claim for any due process violation.
III
[32] Plaintiff next contends that the trial court erred in dismissing its remaining claims for relief on the basis that the requests for additional compensation should have been submitted under the Procedures. In support of this contention, plaintiff asserts that the contract provisions governing the Procedures are ambiguous and must be construed against defendants so that judicial pursuit of these claims is proper. In the alternative, plaintiff argues that these claims are not covered by the language in the contracts. We disagree with both contentions.
A
[33] The issue whether a contract is ambiguous presents a question of law. Cheyenne Mountain School District v. Thompson, 861 P.2d 711 (Colo. 1993). Here, upon a contractor’s unsuccessful submission of a claim for additional compensation, the applicable provision required that the “disputes regarding the contract” be resolved by the Manager. As noted, the contracts authorized additional compensation for design errors, differing site conditions, a change in time of performance, or payment.
B
[35] Plaintiff alleges in its complaint that it was fraudulently induced into executing the contracts, as well as in agreeing to certain change orders by defendants, and that defendants violated the covenant of good faith and fair dealing. However, as noted, it is apparent that the alleged misrepresentations and the acts complained of address a “differing site condition” under the applicable provisions of the contracts.
Page 426
should have been undertaken pursuant to the Procedures.
[37] Because of the foregoing resolution of plaintiff’s contentions, it is unnecessary to address defendants’ assertion that plaintiff’s claims are barred by the Governmental Immunity Act, § 24-10-101, et seq., C.R.S. (1988 Repl. Vol. 10A). [38] Further, while the parties addressed on appeal whether the contracts constituted adhesion contracts, plaintiff failed to present that contention in the trial court, and thus, we do not address that issue for the first time here. See Matthews v. Tri-County Water Conservancy District, 200 Colo. 202, 613 P.2d 889(1980). [39] The judgment is affirmed. [40] JUDGE BRIGGS and JUDGE TAUBMAN concur.