No. 99CA0477.Colorado Court of Appeals.
September 14, 2000.
Appeal from the District Court of Eagle County, Honorable Richard H. Hart, Judge, No. 96CV388.
JUDGMENT AFFIRMED IN PART, REVERSED IN PART, AND CAUSE REMANDED WITH DIRECTIONS.
Page 1225
[EDITORS’ NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.]Page 1226
Haligman Lottner Rubin Fishman, P.C., Richard I. Brown, Curt Todd, Michelle Hargis Dillard, Denver, Colorado, for Plaintiff-Appellant and Cross-Appellee.
Page 1227
Collins and Cockrel, P.C., Paul C. Rufien, Derek G. Passarelli, Denver, Colorado, for Defendants-Appellees and Cross-Appellants.
Division II.
Plank and Pierce[*] , JJ., concur.
Opinion by JUDGE DAILEY
[1] In this contract dispute, plaintiff, Interbank Investments, LLC, appeals the trial court’s dismissal of its complaint against defendants, Vail Valley Consolidated Water District and Eagle River Water and Sanitation District. According to plaintiff, the trial court erred in finding that its claims were precluded by the statute of limitations and that it had not, in any event, proven damages with respect to its breach of contract claims. [2] Defendants cross-appeal the trial court’s determinations that plaintiff had standing to sue; that there had not been a material breach of contract precluding recovery here; and that, under the circumstances, repudiation could not be presented as an affirmative defense. [3] We affirm the defendants cross-appeal several of the trial court’s rulings. We affirm in part, reverse in part, and remand with directions. I. Background
[4] Plaintiff claims to be the successor in interest to a developer who in the 1970’s agreed construct two water distribution systems for a water district in Eagle County. Defendants are the successors in interest to the original water districts.
II. Plaintiff’s Standing
[11] Defendants contend that plaintiff has no standing to sue with respect to the 1978 and 1979 agreements, because plaintiff is not in fact a successor in interest to the developer. According to defendants, plaintiff was not properly assigned successor rights under the agreements. We disagree.
Page 1228
the water districts’ consent to any assignments. Because the water districts or defendants never consented to any assignments, defendants argue that the plaintiff is not a valid party in interest.
[13] “Under the law of assignments . . . the right to receive money due or to become due under an existing contract may be assigned even though the contract itself may not be assignable.”Farmers Acceptance Corp. v. DeLozier, 178 Colo. 291, 294, 496 P.2d 1016, 1017 (1972). [14] Defendants argue that this rule is not applicable here because the developer had continuing obligations for any non-performance on its part. However, the agreements provided only a one-year warranty on the water systems and the developer was under no contractual obligation to remedy problems with the systems beyond that date. Further, the developer explicitly assigned only the rights to receive payment, and not any of its obligations under the contract, to its successors in interest, including plaintiff. Hence, defendants’ lack of consent to the assignment of rights to receive payment to plaintiff does not deprive plaintiff of standing to sue.III. Statute of Limitations
[15] Plaintiff assertss that the trial court erred in determining that its claims were time barred. Specifically, plaintiff contends that its claims could not have accrued until after the water districts received sufficient tap fees to recoup their expenses and that the court applied the incorrect limitations period. We agree.
A. Date Cause of Action Accrued
[16] Plaintiff argues that the trial court erred in determining that its claim accrued on July 31, 1984 rather than in October 1990 and May 1992 when the water districts were first under an obligation to pay tap fees to the developer or its successor in interest. We agree.
Page 1229
[24] Indeed, a breach that is material “goes to the root of the matter or essence of the contract,” 6 W. Jaeger, Williston onContracts 3d Ed. § 842 at 165 (3d ed. 1962); see also Gibson v.City of Cranston, 37 F.3d 731 (1st Cir. 1994), and renders substantial performance under the contract impossible. See John D. Calamari Joseph M. Perillo, Contracts § 11-18 at 461-62 (3d eEd. 1987) (“Substantial performance is the antithesis of material breach. If it [is] determined that a breach is material, it follows that substantial performance has not been rendered.”).See also Reynolds v. Armstead, 166 Colo. 372, 443 P.2d 990(1968). [25] In deciding whether a breach is material, the extent to which an injured party would still obtain substantial benefit from the contract, and the adequacy of compensation in damages for the breach, should be considered. Kaiser v. Market Square Discount Liquors, Inc., 992 P.2d 636 (Colo.App. 1999). The importance or materiality of contract terms must be assessed in context and in light of the expectations of the parties at the time the original contract was formed.Phoenix Power Partners, L.P. v. Colorado Public UtilitiesCommission, 952 P.2d 359 (Colo. 1998). [26] Finally, whether a breach of contract is material is a question of fact. Kaiser v. Market Square Discount Liquors, Inc.,supra. Hence, we may disturb the trial court’s finding here only if it is clearly erroneous and not supported by the record. SeeR.A.S. Builders, Inc. v. Euclid Commonwealth Associates, 965 P.2d 1242 (Colo. 1998). [27] The trial court found, with adequate record support, that the developer’s breach in failing promptly to turn over the required documentation was nonmaterial. The developer had performed the essence of the agreements, i.e., building the water systems and turning them over to the water districts to operate. While the non-production of bills of sale, easement conveyances, and as-built drawings in 1984 was not wholly insignificant, this did not obstruct the water district’s use of the water systems,. Most of the documentation, or its equivalent, was ultimately provided to the water districts, and the water districts failed to show how they were damaged therefrom. Similarly, the developer’s failure to produce cost documentation did not interfere with the water district’s use and enjoyment of the water systems; if anything, it was harmful to the developer and its successors in interest, not to the water districts and their successors in interest. [28] The breach, quite simply, did not deprive the water districts of the benefit of their bargains. See Mobil Oil ExplorationProducing Southeast, Inc. v. United States, ___ U.S. ___, 120 S.Ct. 2423, 147 L.Ed.2d 528 (2000). [29] Because the developer did not materially breach the agreements, it follows that defendants were not justified in attempting to terminate or repudiate the agreements in July 1984. When, therefore, defendants repudiated the contract before their time for performance had arrived, the developer could respond by terminating the contract, urging retraction of the repudiation, or ignoring the repudiation and awaiting time for performance. 2 E. Allan Farnsworth, Farnsworth on Contracts § 8.22 at 480 (1990). [30] Here, the developer, having already built the water systems, chose to ignore the repudiation. Consequently, Because the non-repudiating party need not elect to terminate the contract, the contracts would is not be considered actually breached until the time performance was due, i.e., October 1990 and May 1992, and if termination is not chosen, no cause of action has yet accrued and the statute of limitations would not begin to run until that time. Id., supra. See also 4 A. Corbin, Corbin on Contracts § 989 at 967 (1951) (“The plaintiff should not be penalized for leaving to the defendant an opportunity to retract his wrongful repudiation; and he would be so penalized if the statutory period of limitation is held to begin to run against him immediately.”).
B. Applicable Limitations Period
[31] Plaintiff contends that the trial court should not have applied the generic, three-year contract limitations period for causes of actions accruing in 1990 and 1992, but rather generic contract claims. should have applied the more specific, six-year limitations period for actions “to recover a liquidated debt or unliquidated, determinable amount of money due . . .” set out in § 13-80-103.5(1)(a), C.R.S. 2000. We agree.
Page 1230
(Colo. No. 99SC166, 2000), are technically subject to an equitable laches rather than a legal statute of limitations analysis. Absent extraordinary circumstances, however, a court “`will usually grant or withhold relief in analogy to the statute of limitations relating to actions at law of like character.'” Brooks v. Bank of Boulder, 911 F. Supp. 470, 477
(D.Colo. 1996) (quoting Shell v. Strong, 151 F.2d 909 (10th Cir. 1945)). Hence, because plaintiff did not present any evidence of extraordinary circumstances, we, like the trial court, will apply the statute of limitations analysis applicable to plaintiff’s contract claims to the laches analysis applicable to the unjust enrichment claims.
C. Application to Facts
[38] Applying the six-year debt statute of limitation, plaintiff’s breach of contract and unjust enrichment claims on the 1979 agreement, which accrued in May 1992, were timely filed.
(Colo.App. 1992). [40] Here, plaintiff was not entitled to recovery of the entire amount due it under the 1978 agreement in October 1990. Rather, plaintiff was entitled to compensation, bit by bit, as tap fees were collected. All but one of the scheduled tap fees payable to plaintiff under the 1978 agreement fell within the applicable limitations period because they were recovered after October 1990. Consequently, most of plaintiff’s contract claim survived the statute of limitations. So too did plaintiff’s unjust enrichment claim. To hold otherwise would result in a virtual forfeiture of plaintiff’s interests, and “equity abhors [a] forfeiture.” SeeGrombone v. Krekel, 754 P.2d 777, 779 (Colo.App. 1988) (“It is fundamental law that equity abhors forfeiture.”).
Page 1231
[41] Plaintiff’s breach of contract and unjust enrichment claims on the 1979 agreement were timely filed because those claims first accrued only in May 1992, and plaintiff’s lawsuit was filed within six years thereof. IV. Plaintiff’s Failure to Prove Contract Damages
[42] Plaintiff contends that the trial court also erred in finding that it had failed to prove its contract damages under the 1978 and 1979 agreements. We disagree.
(Colo. 1993);. see also Kaiser v. Market Square Discount Liquors,Inc., supra. If the amount of loss is not satisfactorily proved, a small sum fixed without regard to the actual amount of loss will be awarded as nominal damages. General Insurance Co. of Americav. City of Colorado Springs, 638 P.2d 752 (Colo. 1981); Doyle v.McBee, 161 Colo. 130, 420 P.2d 247 (1966). [44] As fact finder, the trial court has the sole prerogative for fixing the amount of damages, and its award will not be set aside unless it is manifestly and clearly erroneous. Kinckaid v.Western Operating Co., 890 P.2d 249 (Colo.App. 1994). [45] Here, the trial court found that plaintiff failed to prove the amount of its damages by a preponderance of the evidence. The trial court noted that: (1) plaintiff attempted to prove its damages through summarized final draw requests, some bills, and unexplained apportionments of purported tank and engineering costs; (2) plaintiffs had not complied with the contractual requirement to provide precise construction documents and invoices with respect to the two agreements; (3) no documents succinctly stated plaintiff’s claims; (4) no invoices were supplied from which the court could reliably determine the costs incurredfirst; and (5) the proof at trial did not support a calculation of an amount of actual damages first. [46] Because the sufficiency, probative effect, and weight of the evidence, and the inferences and conclusions drawn from it, were within the province of the trial court, see generally Goluba v.Griffith, 830 P.2d 1090 (Colo.App. 1991), we can not disturb its determination here. Consequently, we uphold the trial court’s ruling and conclude that plaintiffs are entitled only to nominal damage awards on their contract claims. See GeneralInsurance Co. of America v. City of Colorado Springs, supra.
V. Repudiation Defense
[47] Finally, on cross-appeal, Defendants also assert that the trial court erred in striking their affirmative defense of repudiation. We disagree.
VI. Disposition
[51] We have concluded that plaintiff was not time-barred from instituting an action with respect to most of its breach of contract claim regarding the 19789 agreement, its breach of contract claim regarding the 1979 agreement, and its unjust enrichment claims regarding both agreements.
Page 1232
the doctrine of unjust enrichment “may apply” and that unjust enrichment awards “might be” appropriate in connection with the 1978 and 1979 agreements. Given the tentative nature of these rulings, we are unable to determine whether plaintiff should recover restitution for unjust enrichment in lieu of the nominal damage awards. See E. H. Boly Sons, Inc. v. Schneider, 525 F.2d 20, 23 (9th Cir. 1975) (n. 3) (“while damages and restitution cannot be requested concurrently in a complaint, a plaintiff may claim these as alternatives, leaving the ultimate election for the court”).
[54] Consequently, on remand, the trial court must determine whether plaintiff is entitled to recover restitution for unjust enrichment and, if so, in what amount. Only then can the trial court fashion an appropriate judgment in this case. [55] Accordingly, those parts of the trial court’s judgment recognizing plaintiff’s right to sue; determining that no material breach precluded recovery; holding that repudiation could not be an affirmative defense here; and finding that damages for the contract claims were not proven, are affirmed. That portion of the judgment in which the trial court concluded that plaintiff’s claims were time-barred is reversed, and cause is remanded for further proceedings on plaintiff’s unjust enrichment claims. [56] JUDGE PLANK and JUDGE PIERCE concur.Page 426