No. 89SC240Supreme Court of Colorado.
Decided July 9, 1990. Rehearing Denied September 10, 1990.
Certiorari to the Colorado Court of Appeals
Page 484
Faegre Benson, Diane B. Davies; Bosworth Towey, P.C., Edward B. Towey, J. Scott Needham, for Petitioner.
Bauer Durkin, P.C., Douglas S. Durkin, for Respondents Stan Miller, Inc. and Robert A.M. Stern d/b/a Robert A.M. Stern Architects.
Alexander F. Rolle, for Respondents Merrick Co., Virginia Drilling Co., Inc., and Jonathan Rovick and Jeff Page d/b/a Western Slope Forestry.
Holme, Roberts Owen, G. Kevin Conwick, for Respondent Delaware Associates, Ltd.
French, West, Wood Brown, P.C., John B. Wood, for Respondent Breckenridge Building Center.
Respondents Raymond Strahlo d/b/a Raymond Construction, and Breckenridge Resort Associates, Inc., a Colorado corporation, d/b/a Breckenridge Associates, Inc. not appearing.
EN BANC
JUSTICE ERICKSON delivered the Opinion of the Court.
[1] We granted certiorari to consider whether a blanket mechanics’ lien should have been apportioned, and whether late charges contained in a contract between a landowner and contractor are entitled to the protection of the Colorado General Mechanics’ Lien statutes. See §§ 38-22-101to -133, 16A C.R.S. (1982 1989 Supp.). The court of appeals held that the district court did not abuse its discretion in refusing to order pre-sale apportionment or partial redemption of the property, and that petitioner Independent Trust Corporation (ITC) waived the issue of whether contractual late charges are lienable. Stan Miller, Inc. v. Breckenridge Resort Assocs., Inc., 779 P.2d 1365 (Colo.App. 1989). In the alternative, the court of appeals found that late charges were covered by the mechanics’ lien statutes. Id. at 1370. It therefore affirmed the judgment of the district court on these issues.[1] We affirm the court of appeals on the apportionment and redemption questions, but reverse on the issues of waiver and lienability of contractual late charges.
I
[2] Respondent Breckenridge Resort Associates, Inc. (BRAI) purchased approximately 1100 acres of land in Summit County from respondent Delaware Associates, Ltd., on February 28, 1985, for a total purchase price of $14,445,501. Two million dollars of the purchase price was provided by ITC by means of a loan to BRAI secured by a first deed of trust on somewhat less than ten percent of the property (ITC property), and a second deed of trust on the remaining 90% of the property (Delaware property), subject to a purchase money first deed of trust held by Delaware. The deeds of trust in effect partitioned the 1100 acres into two contiguous parcels. There is no evidence in the record, however, that BRAI or any of the other parties attached any
Page 485
significance to the division except for purposes of the deeds of trust.
[3] BRAI intended to develop the 1100 acres in phases into a golf and residential resort community to be called Swan Valley. A master plan agreement between Delaware and the Town of Breckenridge, and later assigned to BRAI, reflects a desire to develop the property to a density of 1500 single-family equivalents. The first phase was the development of a large tract of the property located next to the Breckenridge Town golf course. The land to be developed in this first phase included the ITC property. BRAI agreed to construct a temporary clubhouse next to the golf course in order to obtain the town’s consent to the formation of a metropolitan district encompassing Swan Valley. [4] All of the respondent mechanics’ lien claimants were hired by BRAI for work on this Swan Valley project.[2] BRAI located its sales office in a wing of the temporary clubhouse. Unfortunately, BRAI ran into difficulties and none of the mechanics’ lien claimants were paid. In addition, BRAI defaulted on its obligations to Delaware and ITC. [5] This mechanics’ lien action was commenced in Summit County District Court on December 19, 1985, by respondent mechanics’ lien claimants Stan Miller, Inc., Merrick Company, and Robert A.M. Stern d/b/a Robert A.M. Stern, Architects. The action sought, inter alia, a declaration of the priorities and the amounts due the mechanics’ lien claimants. The other respondent claimants, along with petitioner ITC and respondents Delaware and BRAI, were named as defendants. During the pendency of the action, Delaware and ITC foreclosed their first deeds of trust, and became the owners of the Delaware property and the ITC property respectively. [6] The first pretrial conference resulted in the first pretrial order being issued on January 6, 1985. Among other things, the order required the claimants, if they hadPage 486
not already done so, to file affidavits setting out the amount of the mechanics’ liens claimed and the material and labor expended. Any party opposing the amount, reasonableness, or the inclusion of non-lienable items in an affidavit filed by a claimant, was ordered to file a controverting affidavit setting out specific facts within twenty days after the claimant’s affidavit was filed.[3] No affidavits of any kind were filed by ITC in response to the affidavits filed by the claimants, including WSF.
[7] A second pretrial conference was requested to resolve the disagreements of counsel over the scope and effect of the first pretrial order. In this pretrial hearing on April 8, 1987, the district judge ruled that WSF’s claims, and the other mechanics’ lien claims, were “deemed admitted” since no responsive affidavits were filed by ITC. [8] At a pretrial motions hearing held on May 20, 1987, counsel for WSF made an oral motion for summary judgment which was immediately granted from the bench. The district court also granted summary judgment in favor of all the other claimants. A written judgment incorporating these rulings was entered by the court on June 23, 1987. The court held that the claimants were entitled to the full amount of the mechanics’ liens claimed, that the mechanics’ liens had priority over the deeds of trust held by Delaware and ITC,[4] and that, with the exception of Stan Miller’s lien, the mechanics’ liens extended over the entire 1100 acres.[5] [9] Following the oral granting of summary judgment, ITC moved the district court for the first time for pre-sale apportionment of the liens between Delaware and ITC on the basis of the respective acreage owned by each party.[6] The district court held a hearing on this motion and on Delaware’s motion for distribution of the proceeds of the sale on August 17, 1987. [10] At the hearing, ITC’s counsel stated that ITC was in the process of foreclosing on itsPage 487
first deed of trust and that an appraisal revealed that Delaware now owned over 94% of the property, rather than the presumed 90 or 91%. Counsel for ITC then offered the testimony of an appraiser as to the value of the property as a whole ($9.375 million), and the value of the Delaware property ($8.975 million). The district court refused to admit the testimony, finding it irrelevant because ITC in its motion asked for apportionment based on acreage, not value. The district court found the language in the motion asking the court to take evidence on some other appropriate method of apportionment too general to preserve the issue. The court then denied the motion for pre-sale apportionment and granted Delaware’s motion for distribution of the proceeds following the sale.[7]
The district court ordered a foreclosure sale of the property as a whole. On appeal, the court of appeals affirmed the district court’s judgment except for the award of attorney’s fees to Delaware. See
footnote 7.
II
[11] ITC first contends that the district court erred in failing to order pre-sale apportionment of the mechanics’ lien claims. The right to a mechanics’ lien is wholly a creature of statute,[8] and although all fifty states recognize some form of mechanics’ lien, the statutes have significant differences. See 3 R. Powell P. Rohan, Powell on Real Property ¶ 483, at 735 (1990). Thus in interpreting the Colorado mechanics’ lien law, cases from other jurisdictions should be approached with caution. Section 38-22-103(4) provides:
Page 488
[13] (Emphasis added.) This subsection, which permits a lien claimant to apportion the lien if possible, also allows the claimant to file a blanket lien if the work “cannot be readily and definitely divided and apportioned . . . .” In Buerger Investment Co. v. B.F. Salzer Lumber Co., 77 Colo. 401, 407, 237 P. 162, 165 (1925), we interpreted the predecessor to subsection 38-22-103(4) and said: [14] “The reasonable, liberal and equitable construction of these terms is that the claimant may apportion where possible; if impossible, he must spread his blanket, but if apportionment is possible, yet cannot readily be made, he may choose whether he will apportion or file a blanket lien. . . . We think [a claimant] may in good faith choose the blanket lien and make his statement so, and, if it turns out that an apportionment is readily possible and the court deems it equitable to all parties, it may be had in the decree.” [15] See also Plateau Supply Co. v. Bison Meadows Corp., 31 Colo. App. 205, 212, 500 P.2d 162, 167 (1972) (where work was done as a part of the entire project and could not be “readily and definitely divided,” it was proper to file a mechanics’ lien against the entire project). Subsection 38-22-103(4), and our interpretation of it, is in accord with the general rule that a blanket mechanics’ lien upon several properties for materials and labor benefitting the properties may not be enforced against less than all of the properties in the absence of some showing of proper apportionment. See Annotation, Enforceability of Single Mechanic’s Lien Upon Several Parcels Against Less Than the Entire Property Liened, 68 A.L.R.3d 1300, 1303 (1976 Supp. 1989). [16] The questions for decision are whether ITC presented sufficient evidence to establish that the claimants’ work could be “readily and definitely divided” between the ITC property and the Delaware property; or whether equity and good conscience required apportionment, see Associated Sand Gravel Co. v. DiPietro, 8 Wn. App. 938, 943, 509 P.2d 1020, 1024 (1973). [17] We agree with the court of appeals in the conclusion that ITC failed to discharge its burden of proof on either issue. ITC introduced no evidence on how the materials provided and labor performed by the claimants could be readily divided between the ITC and Delaware properties. At most, ITC asked for apportionment based on the relative acreage, and attempted to introduce evidence of the relative values of the two parcels after foreclosure of the deeds of trust. Neither of these methods was sufficient as a matter of law to demonstrate that the value of the work was readily divisible. [18] Nor has ITC satisfied its burden of showing that the district court should nevertheless in equity and good conscience have apportioned the liens. Cf. Joralmon v. McPhee, 31 Colo. 26, 39-40, 71 P. 419, 423 (1903). Any showing made by ITC that failure to apportion may result in unfairness to ITC is outweighed by the equities in favor of the mechanics’ lien claimants, who performed their work in 1984 and 1985 and still have not been paid, and by the failure of ITC to present a reasonable and consistent method of apportionment. Absolute fairness inter sese the owners of the property liened is not a priority of the general mechanics’ lien law. See Howard v. Fisher, 86 Colo. 493, 519, 283 P. 1042, 1052 (1929) (“The [mechanics’ lien] statute contemplates a speedy determination of claims, to the end that mechanics’ lienors will not have to wait indefinitely for their money, or for experiments in legal procedure.”). [19] The cases cited by ITC to support apportionment are distinguishable. In Brunzell v. Lawyers Title Insurance Corp., 101 Nev. 395, 705 P.2d 642(1985), the Nevada Supreme Court held that the trial court did not err in ordering apportionment of mechanics’ liens on a condominium project where there was no evidence that the cost of the project was not equally divisible among the units. In contrast, the property here, as the district court found, was benefitted as a whole by the work performed, and the value of the work was not readily divisible by units. [20] In Sebastian Building Loan Association v. Minten, 181 Ark. 700, 27 S.W.2d 1011 (1930), and Manchester Iron Works,
Page 489
Inc. v. E.L. Wagner Construction Co., 341 Mo. 389, 107 S.W.2d 89 (1937), the courts confirmed the equitable power of a trial court to apportion or allocate the value of materials and labor provided under a contract to more than one house. At the time the mechanics’ lien claimants tried to enforce their liens, the houses had passed into the hands of third parties. It was possible to determine with reasonable certainty the value of the work performed on each house, and apportionment was justified to prevent inequity to the third parties. These cases are not inconsistent with the result here.
[21] West Alexandria Properties, Inc. v. First Virginia Mortgage and Real Estate Investment Trust, 221 Va. 134, 267 S.E.2d 149 (1980) and PIC Construction Co. v. First Union National Bank of North Carolina, 218 Va. 915, 241 S.E.2d 804 (1978) dealt with the partial release of a mechanics’ lien claim and the subsequent attempt by the claimant to enforce the lien against the remainder of the property. Both cases are inapposite to the issues presented here.[9] [22] We conclude that, on this record, the district court did not abuse its discretion in refusing to order pre-sale apportionment of the mechanics’ liens. III
[23] ITC next argues that the district court erred in ordering a sale of the entire property without allowing partial redemption.[10] The general rule in Colorado is that, in the absence of a statute to the contrary, property sold as a whole must be redeemed as a whole. Walker v. Wallace, 79 Colo. 380, 384-85, 246 P. 553, 554 (1926); Pheney v. Western Nat’l Bank, 762 P.2d 693, 695 (Colo.App. 1988). Redemption by an owner of property sold at a lien foreclosure sale is governed by section 38-39-102, which provides that
turned on the redemption rights under section 38-39-103 of a junior lienor with a lien on only one joint tenant’s interest in the property. We decline to extend the holding in Energy Fuels Corp. to require partial redemption whenever more than one landowner is entitled to statutory redemption. The district court did not err in refusing to order partial redemption before the sale was held.[11]
Page 490
IV
[27] Finally, ITC argues that WSF’s contractual late charges are not entitled to the protection of the general mechanics’ lien law. In particular, late charges are not subject to a mechanics’ lien because they are not related to the “value of . . . services rendered or labor done or material furnished . . . .” § 38-22-101(1), 16A C.R.S. (1982).[12]
The court of appeals found that ITC waived the defense of non-lienability by not filing an affidavit in response to the affidavit of WSF. In the alternative, the court of appeals held that contractual late charges are subject to the mechanics’ lien law. We take up first whether ITC waived the defense.
A
[28] In its “Counterclaim and First Cross-Claim,” WSF alleged that:
Page 491
defenses founded upon an assertion of an excessive lien. Except as otherwise provided in this order, issues for trial on the aforementioned matters required to be set forth by responsive affidavits shall be limited to the specific grounds and matters asserted in those affidavits; all other facts concerning those matters shall be deemed admitted.”
[38] Stan Miller, Inc. v. Breckenridge Resort Assocs., Inc., No. 85CV588, slip op. at 2-3 (Dist. Ct. Jan. 6, 1987) (pretrial order) (emphasis added). ITC objected to the proposed pretrial order in a letter from ITC’s counsel dated December 22, 1986. All of counsel’s objections were incorporated into the order. [39] Following the pretrial order, WSF filed the affidavit of Jonathan E. Rovick, dated January 7, 1987. It states in relevant part: [40] “COMES NOW the undersigned Jonathan E. Rovick, being first duly sworn, and states as follows: [41] “1. Jonathan E. Rovick and Jeff C. Page, d/b/a Western Slope Forestry (“WSF”) provided tree clearing services on the real property that is the subject of this action pursuant to contract with defendant Breckenridge Resort Associates, Inc. These services were incorporated into the project. [42] “2. As of December 12, 1986, WSF is owed $52,769.96 for services rendered and accrued late charges, plus recording costs in the amount of $72.00 and filing fees in the amount of $75.00, for a total of $52,916.96. WSF has also incurred attorneys’ fees in an amount to be proven at trial. [43] “3. Late charges continue to accrue at the rate of $92.14 per diem. [44] ITC filed no affidavit in response to the WSF affidavit, although BRAI did file an affidavit that challenged the amount of WSF’s charges in general. In a motion for summary judgment filed on January 23, 1987, ITC did not specifically dispute the validity of WSF’s late charges. The motion alleged that ITC’s first deed of trust was entitled to priority over the mechanics’ liens, and raised the issue whether the liens could be maintained against the whole of the property. [45] In a motion requesting a second pretrial conference, WSF noted that ITC [46] “failed to submit any affidavits in opposition to the mechanic’s lien affidavits that were filed. Accordingly, these lien claimants and the other lien claimants in this case maintain that Independent Trust Corporation is now foreclosed from presenting any defenses to the mechanic’s lien claims at trial. Nevertheless, counsel for defendant Independent Trust Corporation has indicated that she regards all defenses as open to Independent Trust Corporation.” [47] On March 9, 1987, ITC filed a “Reply Brief in Response to Responsive Brief of Merrick and Others [including WSF] in Opposition to Independent’s Motion for Summary Judgment.” It stated in part: [48] “The instant claimants also mischaracterize the Affidavit process called for by the written Pretrial Order entered by the Court. That order did not, as the instant claimants contend, require opposing Affidavits on the issues of the quality, scope and priority of the claimant’s work. It required such Affidavits only on “the amount claimed and incorporation of materials and labor in the project”, and that was what was done. The issues of priority, and which land and to what extent, if any, the liens attached thereto, were to be encompassed in the Motion for Summary Judgment directed to be filed by Independent Trust The question of the reasonableness of the amounts claimed, being a legal one, was, by its very nature, left to be resolved by the Court at trial.” [49] (Emphasis added.) The remainder of the brief addressed the issues of priority and whether the liens should extend to the entire property. [50] Because of the disagreements of counsel over the scope and effect of the first pretrial order, a second pretrial conference was held on April 8, 1987. At this conference, counsel for ITC brought up the matter of the “reasonableness” and lienability of WSF’s late charges, but the districtPage 492
judge, who was not the judge who presided at the first pretrial, ruled that those claims, and the other mechanics’ lien claims, were “deemed admitted” since no responsive affidavits were filed by ITC.
[51] At a pretrial motions hearing held on May 20, 1987, the district court reiterated that, based on the first pretrial order, ITC had waived the issues of the “validity of the mechanic’s liens and the reasonableness of the values, as well as the priority of those mechanic’s liens over that of I.T.C.’s deed of trust,” and granted WSF’s motion for a summary judgment. [52] We conclude that ITC did not intend to waive the defense that WSF’s late charges were non-lienable. The record reveals that ITC’s counsel consistently maintained that the pretrial order did not require her to file an affidavit opposing the inclusion of the late charges because she believed that the lienability issue was one of law for the court to decide which would not be decided on the basis of specific facts in an affidavit. Counsel for ITC was wrong. The plain import of the pretrial order was to require ITC to file opposing affidavits to preserve the issue of inclusion of non-lienable items. [53] Pretrial conferences and orders are tools for simplifying the issues with an eye toward ultimately resolving lawsuits on the merits, not methods for avoiding trials altogether. See Padovani v. Bruchhausen, 293 F.2d 546, 548 (2d Cir. 1961)[13] ; Glisan v. Kurth, 153 Colo. 102, 108, 384 P.2d 946, 949 (1963). The rule governing summary judgment is Rule 56 and the affidavit filed by WSF by itself did not entitle WSF to judgment as a matter of law on the matter of late charges. See Ginter v. Palmer Co., 196 Colo. 203, 206, 585 P.2d 583, 585 (1978). Summary judgment was proper, therefore, only if the district court had the power to modify the requirements of Rule 56 through the pretrial order entered pursuant to Rule 16, either inherently or with the consent of ITC. [54] Assuming without deciding that a pretrial order under C.R.C.P. 16 can have the effect of dispensing with the requirements of Rule 56 for summary judgment,[14] we find that under the facts of this case, the pretrial order should have been modified to allow ITC to contest the lienability of the late charges to prevent manifest injustice. Ferguson v. Hurford, 132 Colo. 507, 520, 290 P.2d 229, 236 (1955). [55] A number of factors have entered into our conclusion. First, in the absence of the pretrial order, ITC would not have been required to file a controverting affidavit to raise the issue of the inclusion of late charges, since the issue is purely one of law. Second, counsel for ITC consistently maintained, albeit mistakenly, that the pretrial order did not require her to file an affidavit to preserve the legal defense to the lienability of late charges. Third, the court granted WSF’s oral motion for summary judgment from the bench apparently catching ITC’s counsel unaware and without allowing for a response from ITC. Fourth, the consequences of counsel’s mistake would fall heavily on the client. There is nothing in the record to show that ITC intended to waive the defense of lienability to late charges, or directly participated in disobeying the pretrial order so as to share in the blame. Fifth, we hold that the contractual late charges here are not lienable under section 38-22-101, and thePage 493
settling of this issue is of importance beyond the interests of the parties in this case, so the defense is meritorious. Finally, consideration of the non-lienability defense will not unduly prejudice WSF or the other appellees, or result in further delay, since a trial will not be required. The issue can be decided as a pure question of law, and remand is unnecessary because the court of appeals has already considered the lienability issue on the merits.
B
[56] The court of appeals determined that contractual late charges were entitled to inclusion in the mechanics’ lien claim because in situations where “it is undisputed that the lien claimant fully performed its contract with the owner, the claimant is entitled to the entire contract price.”Stan Miller, Inc. v. Breckenridge Resort Assocs., Inc., 779 P.2d at 1370. The court of appeals holding was based on their interpretation of section 38-22-101(2), which provides:
(Colo.App. 1989); Lindemann v. Belden Consol. Mining Milling Co., 16 Colo. App. 342, 346, 65 P. 403, 404 (1901). [60] Until the court of appeals opinion in this case, the case law had limited a mechanics’ lien claimant’s recovery to the value of the materials, labor, or services provided. Thirteenth St. Corp. v. A-1 Plumbing Heating Co., 640 P.2d 1130, 1133-34 (Colo. 1982); Heating Plumbing Eng’rs v. H.J. Wilson Co., 698 P.2d 1364, 1367 (Colo.App. 1984). The court of appeals in this case distinguished Heating Plumbing Engineers on the basis that the contract in that case had not been entirely performed. While that is a factual difference between the cases, the court of appeals reads the holding in Heating Plumbing Engineers too narrowly. [61] We agree with the court of appeals in Heating Plumbing Engineers
that subsection (2) must be read in conjunction with subsections (1) and (3). Subsection (2) does not enlarge the rights of a contractor to a mechanics’ lien for the full contract price over and above the value of the materials provided and services and labor performed. Rather, if the owner timely records the contract pursuant to subsection 38-22-101(3), the contract price becomes a ceiling for the total amount of mechanics’ liens that can be asserted against the property arising out of the contract. § 38-22-101(3), 16A C.R.S. (1982); Stewart v. Talbott, 58 Colo. 563, 574, 146 P. 771, 775 (1915).[15] [62] When there is a written contract between the owner of the property and the lien claimant for labor to be performed and materials to be used on the property sought to be charged, and when the labor
Page 494
is actually performed and the materials are used on the property, cf. Heating Plumbing Eng’rs, Inc. v. H.J. Wilson Co., 698 P.2d at 1367, the contract price is a good indication of the value of the goods and labor entitled to the lien. Late charges are not mentioned as items lienable under the statute, and thus WSF’s lien may not extend to the late charges.[16]
[63] Accordingly, we affirm the judgment of the court of appeals with respect to the issues of apportionment and partial redemption. We reverse the judgment of the court of appeals insofar as it affirmed the district court’s inclusion of late charges in the mechanics’ lien awarded to WSF. We return the case to the court of appeals for remand to the district court for further proceedings consistent with this opinion.(1895). The prototype mechanics’ lien statute was enacted by the General Assembly of Maryland in 1791 in response to a request from the Commission that was established to supervise construction of the capitol in Washington. This first statute was limited to the city of Washington and applied only to persons having direct contractual relations with the owners of the land benefitted. See McNab Harlin Mfg. Co. v. Paterson Bldg. Co., 71 N.J. Eq. 133, ___, 63 A. 709, 710-11 (1906); 3 R. Powell P. Rohan, Powell on Real Property ¶ 483, at 733-34 (1990).
§ 38-22-124, 16A C.R.S. (1982).