No. 81CA0644Colorado Court of Appeals.
Decided May 6, 1982. Opinion modified and as modified petition for rehearing denied June 17, 1982.
Appeal from the District Court of Mesa County, Honorable James J. Carter, Judge.
Page 1316
William M. Kane, for plaintiff-appellant and cross-appellee.
Dufford, Waldeck, Ruland, Wise Milburn, Amanda D. Bailey, for defendants-appellees and cross-appellants.
Division III.
Opinion by JUDGE KIRSHBAUM.
[1] This appeal involves a summary judgment entered by the trial court. Plaintiff architectural firm, Chambliss/Jenkins Associates (CJA), appeals the dismissal of its complaint and the denial of its motion to amend the complaint. Defendants, Louise Forster, M. C. Schumann, Betty June Schumann, Harold W. Reeder, Ann Reeder, Alfred B. Carrick, Eula B. Carrick, La Villa Grande, Inc., and Bethesda Care Centers, cross-appeal the dismissal of their counterclaims.[1] We affirm in part and reverse in part. [2] The record reveals the following facts. In the early 1970s, Forster, the Schumanns, the Reeders, the Carricks, and La Villa Grande, Inc., (owners)[2] purchased certain real property in Mesa County, Colorado. They constructed a nursing home on a portion of the property and then proposed to build a retirement center on the remainder. In late 1976, however, they concluded that they could not obtain appropriate financing for the project. [3] During 1976, the owners came into contact with defendant Columbine Village, Inc., (Columbine) a non-profit corporation formed by persons who also desired to develop a “life care” retirement center in Mesa County. In 1977, the owners and Columbine entered into the first of several option agreements for the purchase of the nursing home and adjoining property. [4] Columbine ultimately decided to obtain its financing through the sale of tax-exempt municipal bonds. It engaged the services of Municipal Bond Advisors of America (MBA) for this purpose and obtained new options from the owners extending through July 31, 1979. These options provided for early termination in the event Columbine did not submit written evidence to owners, by May 10, 1979, that MBA had obtained a commitment for the sale of the bonds. [5] On May 10, 1979, Columbine received a letter from MBA stating that MBA had secured a commitment to purchase the bonds and that MBA awaited the “receipt of properly signed documents as previously outlined.” Columbine immediately forwarded this letter to the owners. On May 11, the owners’ selling agent, Edwards, wrote a letter to Columbine that contained the following pertinent language: [6] “This letter will serve to remove the contingencies contained in the Addendum to both option agreements referred to above, whereby Municipal Bond Advisors of America, Inc. was to submit written evidence regarding the bond issue. [7] “Principals and LaVilla Grande have accepted the written evidence submitted by Municipal Bond Advisors of America, Inc. subject to the following: [8] . . . . [9] “2. The documents that were discussed in the letter of May 10, 1979 which included the architect’s contract, the contractor’s contract and option agreementsPage 1317
shall be completed on or before 10 days from the date of this letter.”
[10] The letter was hand-delivered to and accepted by Columbine that same day. [11] On May 12, 1979, Columbine executed a written contract with CJA which required CJA to prepare architectural plans and drawings for the proposed life care center in return for a fee of $95,400. In August 1979, owners and Columbine agreed to extend the options through October 1, 1979. The bonds were not purchased when offered for sale, and Columbine elected to forego its options. [12] When Columbine failed to pay for the architectural plans and designs which had been prepared, CJA filed a mechanic’s lien against the interests of the owners, Edwards, and Bethesda Care Center (Bethesda) in the subject property. (Bethesda purchased a portion of the subject property from La Villa Grande, Inc., in 1980.) CJA also filed this foreclosure suit against Columbine, owners, Edwards, Bethesda, others not party to this appeal, and Jack R. Haney, d/b/a J.R. Haney Associates (Haney), an unpaid subcontractor of CJA who had filed his own mechanic’s lien on the property. (CJA obtained a default judgment against Columbine; the dispute between CJA and Haney has been resolved.) [13] The owners and Bethesda jointly filed a motion for summary judgment requesting dismissal of CJA’s complaint and of Haney’s cross-claim on the ground that the asserted mechanic’s liens were invalid. CJA filed a motion for partial summary judgment, requesting an adjudication of the validity of its lien statement. No party requested summary judgment on the counterclaims and cross-claims of the owners and Bethesda against CJA and Haney. [14] Ruling that CJA had not established any right to impose a mechanic’s lien on the subject property, the trial court granted the motion of the owners and Bethesda to dismiss CJA’s complaint. The trial court also dismissed defendants’ counterclaim “as unproven.” The trial court did not rule on Haney’s cross-claim, as requested by the owners and Bethesda in their summary judgment motion. And, contrary to the statements of the owners, Bethesda, and Edwards in their appellate briefs, the record reveals that the trial court did not dismiss their cross-claims against Haney. In denying post-trial motions filed by the owners, Bethesda, and Edwards and by CJA, the trial court held “that this determination shall provide a final judgment at the trial court level for all purposes of appellate review.” We conclude that this language sufficiently complies with the requirements of C.R.C.P. 54(b). [15] I. APPEAL OF CJA
[16] CJA contends that the trial court erred in dismissing its complaint against the owners and Bethesda. We agree.
Page 1318
James H. Stewart Associates, Inc. v. Naredel of Colorado, Inc., 39 Colo. App. 552, 571 P.2d 738 (1977).
[21] While an owner is not subject to an architect’s lien under this statute unless he or a person authorized by him has contracted for the architect’s services, an owner who, as here alleged, directly authorizes another to hire an architect to draft plans for improvements on the owner’s property may be subject to such a lien. See Colorado Gold Dredging Co. v. Stearns-Roger Mfg. Co., 60 Colo. 412, 153 P. 765 (1916). [22] CJA concedes that the owners did not directly request the performance of architectural services here. CJA contends, however, that the May 11, 1979, letter establishes that Columbine was acting by the authority of or under the owners when it secured CJA’s services, and that the hiring of an architect became a term of the option agreements. Thus, the legal significance of that correspondence is critical for the determination of this issue. [23] When an agreement between parties is contained in more than one instrument, those instruments must be construed together as though they comprised a single document. Fuller Co. v. Mountain States Investment Builders, 37 Colo. App. 201, 546 P.2d 977 (1975). Further, written documents containing ambiguities or unclear language must be construed in accordance with the intent of the parties, and relevant extraneous evidence may be considered to resolve the factual question of the parties’ intent. Palipchak v. Kent Construction Co., 38 Colo. App. 146, 554 P.2d 718 (1976). [24] Here, the May 11, 1979, letter is ambiguous when read in conjunction with the option agreements, see People v. Johnson, 199 Colo. 248, 618 P.2d 262 (1980); Hahl v. Langfur Construction Corp., 529 P.2d 1369Page 1319
repair, or other improvement” of any building, structure, or other improvement situated upon or in owners’ property. Hence, § 38-22-105, C.R.S. 1973, does not authorize the filing of a lien by CJA.
[30] CJA finally contends that the trial court abused its discretion in denying its motion for leave to amend the complaint. We disagree. [31] In its motion for leave to amend its complaint, CJA asserted that it was advised that Frederick A. Schumann had purchased a portion of the subject real property; that as an owner of the property Schumann was a necessary party under § 38-22-111, C.R.S. 1973; and that its proposed amended complaint “does not seek to assert a new or additional theories or causes of action against the Defendants herein.” An examination of the proposed amended complaint reveals, however, that CJA did seek to assert a new and additional theory against defendant Edwards. In particular, Edwards, who was not listed in the original complaint as “one . . . of the . . . owners of certain real property located in Mesa County, Colorado,” was named in the proposed first amended complaint as “one . . . of the . . . legal or beneficial owners” of the property. [32] Under these circumstances, without addressing the merits of CJA’s argument that Schumann was a necessary party to the action, see generally Howard v. Fisher, 86 Colo. 493, 283 P. 1042 (1929), we conclude that the trial court did not abuse its discretion in denying CJA’s motion to amend its complaint. See generally H.W. Houston Construction Co. v. District Court, 632 P.2d 563 (Colo. 1981); Varner v. District Court, 618 P.2d 1388[33] II. CROSS-APPEAL OF THE OWNERS AND BETHESDA
[34] The owners and Bethesda contend that the trial court erred in dismissing their counterclaims against CJA. CJA concedes in its reply brief that the trial court erred in this respect. We agree.
494 P.3d 651 (2021)2021 COA 71 The PEOPLE of the State of Colorado, Plaintiff-Appellee, v.…
351 P.3d 559 (2015)2015 COA 46 DeeAnna SOICHER, Plaintiff-Appellant, v. STATE FARM MUTUAL AUTOMOBILE INSURANCE…
292 P.3d 924 (2013)2013 CO 4 Richard BEDOR, Petitioner v. Michael E. JOHNSON, Respondent. No.…
327 P.3d 311 (2013)2013 COA 177 FRIENDS OF DENVER PARKS, INC.; Renee Lewis; David Hill;…
(361 P.2d 138) THE GENERAL PLANT PROTECTION CORPORATION, ET AL. v. THE INDUSTRIAL COMMISSION OF…
Larry N. Wisehart, Plaintiff-Appellant, v. Michael Meganck and Vectra Bank Colorado, NA, Defendants-Appellees. No. 01CA1327.Colorado…