No. 80CA1136Colorado Court of Appeals.
Decided September 23, 1982.
Appeal from the District Court of El Paso County, Honorable Joe A. Cannon, Judge.
Page 89
Sparks, Dix and Enoch, P.C., Kenneth Sparks, for plaintiff-appellee.
Strand and Meadows, P.C., Edwin Strand, for defendant-appellant.
Division II.
Opinion by JUDGE PIERCE.
[1] Defendant, Ingels and Associates, Inc., appeals a judgment entered in favor of plaintiff, Hughes, Inc., which awarded Hughes damages for injuries suffered because of the breach of a construction contract prior to completion of a condominium project. We affirm. [2] The parties entered into a construction agreement on August 11, 1978, concerning improvement of a subdivision. Hughes agreed to perform services as general contractor for Ingels, the owner and developer of the property, and to continue site work and commence construction of the first four of 42 planned units. Ingels was to pay Hughes the cost of each unit, as determined by Hughes. The parties agreed to a pay schedule based on a percentage formula of unit completion and time, which concluded with this paragraph: [3] “Should final agreement not be reached, all of Hughes’ costs and expenses, including, but not limited to, profit and overhead, shall be paid by Ingels at the time it becomes clear that no final agreement will be reached.” [4] On September 5, 1978, Hughes, by letter, tendered cost figures for the construction of each of the four units, to which Ingels responded with concern; nevertheless, Hughes continued construction, and Ingels made all progress payments. [5] In December, Ingels discharged Hughes as the general contractor of the project. In early January 1979, Hughes submitted a demand letter to defendant for the balance due it. Ingels refused to make this payment, and contacted Michael Collins, the architect of the project, to ascertain his opinion regarding money owed to Hughes at that time. Upon examination of the work completed, Collins concluded an amount was due which was less than that demanded by Hughes. [6] Thereafter, this action was filed and the matter was tried to a jury. I.
[7] The principal issue on appeal is whether the evidence warranted use of a jury instruction which set forth the measure of damages applied when an owner breaches a construction contract prior to its completion. See Colo. J.I. 30:40 (2d ed. 1980). The instruction stated in part:
Page 90
damages sufficient to place him in the position in which he would have been had the breach not occurred. Comfort Homes, Inc. v. Peterson, 37 Colo. App. 516, 549 P.2d 1087 (1976). As the evidence was sufficient for the jury to make a final determination regarding the terms of the contract, the submitted jury instruction was proper.
II.
[12] Defendant also contends the trial court erred when it permitted plaintiff to call and cross-examine Collins, the architect, as a witness identified with an adverse party under Colorado Rules of Evidence 611(c). We disagree.
494 P.3d 651 (2021)2021 COA 71 The PEOPLE of the State of Colorado, Plaintiff-Appellee, v.…
351 P.3d 559 (2015)2015 COA 46 DeeAnna SOICHER, Plaintiff-Appellant, v. STATE FARM MUTUAL AUTOMOBILE INSURANCE…
292 P.3d 924 (2013)2013 CO 4 Richard BEDOR, Petitioner v. Michael E. JOHNSON, Respondent. No.…
327 P.3d 311 (2013)2013 COA 177 FRIENDS OF DENVER PARKS, INC.; Renee Lewis; David Hill;…
(361 P.2d 138) THE GENERAL PLANT PROTECTION CORPORATION, ET AL. v. THE INDUSTRIAL COMMISSION OF…
Larry N. Wisehart, Plaintiff-Appellant, v. Michael Meganck and Vectra Bank Colorado, NA, Defendants-Appellees. No. 01CA1327.Colorado…