No. 80CA0293Colorado Court of Appeals.
Decided July 19, 1984. Rehearing Denied August 30, 1984. Certiorari Denied February 19, 1985.
Appeal from the District Court of Summit County Honorable Vasco Seavy, Judge
Page 747
Grant, McHendrie, Haines and Crouse, P.C., Charles H. Haines, Jr., Julia O. Robinson for Plaintiff-Appellant, Cross-Appellee Alfred Brown Company and Third Party
Page 748
Defendant-Appellant, Cross-Appellee General Insurance Company of America.
Gorsuch, Kirgis, Campbell, Walker and Grover, Richard B. Harvey, Carlsen, Greiner Law, Wellington H. Law for Defendants and Third Party Plaintiffs-Appellee, Cross-Appellants.
Division I.
Opinion by JUDGE BERMAN.
[1] The litigation at issue here concerns the construction of the Eisenhower Tunnel on Interstate Highway I-70 at the Continental Divide. Plaintiff, Alfred Brown Company (ABCO), appeals on three grounds from judgments entered in its contract action against defendants: Colorado Department of Highways (CDH); Tippets-Abbett-McCarthy-Stratton; and Al Johnson Construction Company, Gibbons Reed Company, Western Paving Company, and Kemper Construction Company, a joint venture, doing business under the style of Straight Creek Constructors (SCC), and their named bonding companies. SCC cross-appeals the award of moratory interest to ABCO. We affirm. I.
[2] ABCO’s first contention is that SCC breached its contract with ABCO and violated § 24-91-103, C.R.S. (1982 Repl. Vol. 10) by refusing to pay ABCO the $679,000 “talking figure” which had been discussed on December 3, 1970, during certain settlement negotiations between CDH and SCC and that, therefore, the trial court erred in concluding that the $679,000 figure was not binding upon SCC or the court. We perceive no contractual or statutory breach by SCC in its settlement with CDH or ABCO. Rather, the trial court’s findings are supported by the record; therefore, we hold that the trial court did not err in its treatment of the settlement of ABCO’s claim See Page v. Clark, 197 Colo. 306, 592 P.2d 792 (1979).
II.
[3] ABCO’s second contention is that the trial court erred, as a matter of law, in finding that any breaches by SCC of its contract with ABCO were “not such as to void the contract” and in concluding, therefore, that ABCO’s quantum meruit claim must be dismissed. Again, our review of the record supports the trial court’s findings and conclusions. Thus, the trial court was correct in finding that the contract between SCC and ABCO was not void. Page v. Clark, supra.
III.
[4] ABCO’s final contention is that the $750,000 damage award, plus interest at 6% on $400,000 of that award, is inadequate. Specifically, ABCO claims the trial court erred in: (1) failing to include a masonry subcontractor’s overrun of $150,000 in fashioning the general damage award to ABCO; (2) denying quantum meruit recovery to ABCO; and (3) providing a 6% instead of an 8% rate for moratory interest and assessing it only on the amount of $400,000, instead of on the amount of $679,000. SCC cross-appeals for reversal of the award of moratory interest to ABCO. Once again, we disagree with ABCO’s contention of error.
Page 749
$750,000 award into two sums, one of $500,000 (for settlement “instead of $679,000”) and one of $250,000 (for “breaches of SCC . . . from June 1, 1968, to . . . March of 1972”), such itemization of the $250,000 figure is purely speculative since the court did not itself attribute specific damages to any specific times and events.
A.
[7] ABCO’s argument that the masonry subcontractor’s overrun of $150,000 ought to be added to ABCO’s general award of damages simply because ABCO was required to pay that amount to its masonry subcontractor is meritless. ABCO points to no evidence at trial causally tying such excess to any breach of contract by SCC. Furthermore, ABCO points to no evidence at trial or statements in the trial court’s findings and conclusions supporting ABCO’s conclusory statement that “it is clear that the trial court did not consider the masonry subcontractor’s overrun of $150,000 in fashioning the general damage award to ABCO of $250,000.” Under these circumstances, we perceive no error in the amount of general damages awarded by the trial court.
B.
[8] ABCO’s claim for quantum meruit relief is, likewise, without merit. It is true that where a material contractual breach occurs, the aggrieved party can rescind the contract and seek to recover the reasonable value of its services in equity. However, it is a “firmly established” rule of law in Colorado that:
C.
[12] ABCO’s final contention is that the trial court erred in awarding it moratory interest at 6% instead of at 8% and in awarding it interest at that rate on only the sum of $400,000, instead of on the sum of $679,000. SCC cross-appeals for the reversal of the total award of moratory interest to ABCO. We disagree with both ABCO’s contention and with SCC’s contention on cross-appeal.
Page 750
544 F.2d 436 (10th Cir. 1976), cert. denied, 429 U.S. 1094, 97 S.Ct. 1109, 51 L.Ed.2d 541 (1977). The statutory rate of interest in effect for transactions, such as the one at issue here, which were entered into or accrued before July 1, 1975, was 6%. Section 5-12-102, C.R.S. The amendment to § 5-12-102, C.R.S., allowing interest at a rate of 8% does “not operate retrospectively to affect a pre-existing transaction.”Weather Engineering Manufacturing, Inc. v. Pinon Springs Condominiums, Inc., 192 Colo. 495, 563 P.2d 346 1977).
[15] Since the award of interest here was moratory and “wholly independent of statute, . . . [w]hether interest will be allowed [and] at what rate . . . is wholly in the discretion of the trial court.” Heller v. First National Bank, 657 P.2d 992 (Colo.App. 1982). Here, as in Heller, supra, in view of the court’s factual findings, its award of interest is “amply supported and justified.” [16] All remaining contentions of error are without merit. [17] The judgment is affirmed. [18] JUDGE PIERCE and JUDGE TURSI concur.